A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
40
36
45
32
The correct Answer is:B
To solve the problem step by step, we will first determine the work efficiencies of A, B, and C based on the information given in the question.
Step 1: Determine the total work
Let’s assume the total work is 96 units (this is chosen as it is the LCM of the days given).
Step 2: Calculate the work efficiencies
1. A and B together can complete the work in 16 days:
Efficiency of A + B=9616=6 units/day
2. C and A together can complete the work in 32 days:
Efficiency of C + A=9632=3 units/day
3. B and C together can complete the work in 24 days:
Efficiency of B + C=9624=4 units/day
Step 3: Set up equations
From the efficiencies calculated, we can set up the following equations:
1. A+B=6
2. C+A=3
3. B+C=4
Step 4: Solve the equations
We can solve these equations to find the individual efficiencies of A, B, and C.
1. From A+B=6 (Equation 1)
2. From C+A=3 (Equation 2)
- Rearranging gives C=3−A
3. From B+C=4 (Equation 3)
- Substitute C from Equation 2 into Equation 3:
B+(3−A)=4⟹B=1+A
4. Substitute B=1+A into Equation 1:
A+(1+A)=6⟹2A+1=6⟹2A=5⟹A=2.5
5. Now substitute A back to find B and C:
B=1+2.5=3.5
C=3−2.5=0.5
Step 5: Calculate the total efficiency of A, B, and C
Now, we have:
- Efficiency of A = 2.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 0.5 units/day
Step 6: Calculate the total work done in 12 days
When A, B, and C work together for 12 days:
Total efficiency of A + B + C=A+B+C=2.5+3.5+0.5=6.5 units/day
Work done in 12 days=12×6.5=78 units
Step 7: Calculate the remaining work
Remaining work=96−78=18 units
Step 8: Calculate the time taken by C to complete the remaining work
Since C's efficiency is 0.5 units/day, the time taken by C to complete the remaining work is:
Time=Remaining workEfficiency of C=180.5=36 days
Final Answer
C alone will complete the remaining work in 36 days.
---
Let’s assume the total work is 96 units (this is chosen as it is the LCM of the days given).
1. A and B together can complete the work in 16 days:
Efficiency of A + B=9616=6 units/day
Efficiency of C + A=9632=3 units/day
Efficiency of B + C=9624=4 units/day
From the efficiencies calculated, we can set up the following equations:
1. A+B=6
2. C+A=3
3. B+C=4
We can solve these equations to find the individual efficiencies of A, B, and C.
2. From C+A=3 (Equation 2)
- Rearranging gives C=3−A
3. From B+C=4 (Equation 3)
- Substitute C from Equation 2 into Equation 3:
B+(3−A)=4⟹B=1+A
4. Substitute B=1+A into Equation 1:
A+(1+A)=6⟹2A+1=6⟹2A=5⟹A=2.5
5. Now substitute A back to find B and C:
B=1+2.5=3.5
C=3−2.5=0.5
Now, we have:
- Efficiency of A = 2.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 0.5 units/day
When A, B, and C work together for 12 days:
Total efficiency of A + B + C=A+B+C=2.5+3.5+0.5=6.5 units/day
Work done in 12 days=12×6.5=78 units
Remaining work=96−78=18 units
Since C's efficiency is 0.5 units/day, the time taken by C to complete the remaining work is:
Time=Remaining workEfficiency of C=180.5=36 days
C alone will complete the remaining work in 36 days.
Topper's Solved these Questions
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution
Knowledge Check
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
A80 daysB100 daysC120 daysD150 daysA and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
A12013 daysB48013 daysC24013 daysD96013 daysA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगेA12 daysB315 daysC16 daysD513 days
Anil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionA and B complete a piece of work 12 days B and C can complete in 24,days. A and C can complete it in 16 days. In how many days can B alone complete it?
View SolutionA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View Solution