A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?

A

40

B

36

C

45

D

32

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work efficiencies of A, B, and C based on the information given in the question.

Step 1: Determine the total work
Let’s assume the total work is 96 units (this is chosen as it is the LCM of the days given).

Step 2: Calculate the work efficiencies
1. A and B together can complete the work in 16 days:
Efficiency of A + B=9616=6 units/day

2. C and A together can complete the work in 32 days:
Efficiency of C + A=9632=3 units/day

3. B and C together can complete the work in 24 days:
Efficiency of B + C=9624=4 units/day

Step 3: Set up equations
From the efficiencies calculated, we can set up the following equations:
1. A+B=6
2. C+A=3
3. B+C=4

Step 4: Solve the equations
We can solve these equations to find the individual efficiencies of A, B, and C.

1. From A+B=6 (Equation 1)
2. From C+A=3 (Equation 2)
- Rearranging gives C=3A
3. From B+C=4 (Equation 3)
- Substitute C from Equation 2 into Equation 3:
B+(3A)=4B=1+A
4. Substitute B=1+A into Equation 1:
A+(1+A)=62A+1=62A=5A=2.5
5. Now substitute A back to find B and C:
B=1+2.5=3.5
C=32.5=0.5

Step 5: Calculate the total efficiency of A, B, and C
Now, we have:
- Efficiency of A = 2.5 units/day
- Efficiency of B = 3.5 units/day
- Efficiency of C = 0.5 units/day

Step 6: Calculate the total work done in 12 days
When A, B, and C work together for 12 days:
Total efficiency of A + B + C=A+B+C=2.5+3.5+0.5=6.5 units/day
Work done in 12 days=12×6.5=78 units

Step 7: Calculate the remaining work
Remaining work=9678=18 units

Step 8: Calculate the time taken by C to complete the remaining work
Since C's efficiency is 0.5 units/day, the time taken by C to complete the remaining work is:
Time=Remaining workEfficiency of C=180.5=36 days

Final Answer
C alone will complete the remaining work in 36 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

    A80 days
    B100 days
    C120 days
    D150 days
  • A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A12013 days
    B48013 days
    C24013 days
    D96013 days
  • A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
    A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे

    A12 days
    B315 days
    C16 days
    D513 days