A can finish a piece of work in 24 days B in 9 days and C in 12 days B and C start the work but are forced to leave after 3 days. The remaining work was done by A in : a 5 days b 6 days c 10 days d 21/2 days
Correct option c 10 days Explanation: B and C start the work in 3 days they will do8+6 unit/day × 3 days = 42 unitsWork left = 72 – 42 = 30A Will do in = 30/3 = 10 days
Related Solutions
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View SolutionA can do a piece of work in 24 days, B in 9 days and C in 12 days. B and C start the work together, but leave after 3 days. How many days will A take to complete the remaining work?
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View SolutionA , B तथा C किसी काम को क्रमश : 24 दिन 9 दिन तथा 12 दिनों में कर सकते है B और C साथ काम करना आरभ करते है लेकिन 3 दिन बाद वे काम छोड़ देता है शेष काम A कितने दिनों में पूरा करेगा ?
View SolutionA, B and C together can finish a work in 28 days. All three work for 18 days. After that B leaves. If A and C finish the remaining work in 25 days. The work done by A in 2 days is equal to the work done by C in 3 days then in how many days will A, B and C finish the work separately?
View SolutionA, B and C together can do a piece of work in 32 days. They work for 24 days and after that C leaves. A and B together can do the remaining work in 28 days. 1 day work done by A is equal to 2 days work done by B. Then in how many days they together will finish the work?
View Solutionकिसी कार्य को A, B तथा c क्रमशः 24 दिन, 9 दिन व 12 दिन में पूरा कर सकते है। B तथा C कार्य प्रारम्भ करते है , परन्तु उन्हें 3 दिन बाद यह कार्य छोड़ना पड़ता है। शेष कार्य को करने में A को लगा समय है
View SolutionA, B and C can complete a work in 24 days, 9 days and 12 days respectively. B and C start the work but they have to leave it after 3 days. The time taken by A to do the remaining work is
View Solution(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days
View SolutionA, B and C can do a piece of work in 10 days, 15 days and 30 days respectively. A starts the work and B and C work with A on every alternate day. In how many days will the whole work be finished?
View Solution(A+ B) He can do a piece of work in 8 days. B and C separately do the same work in 12 days. A and B work together for 4 days and then A leaves and after 2 days B leaves. After that in how many days will C alone finish the remaining work?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA और B एक काम को क्रमश : 15 दिनों तथा 10 दिनों में ख़त्म कर सकते है वे साथ काम आरंभ करते है लेकिन 2 दिन के बाद B काम छोड़ देता है A शेष काम पूरा करता है तो पूरा काम कितने दिनो में ख़त्म हुआ ?
View Solution