A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
10 days
1012days
5days
6days
The correct Answer is:A
To solve the problem step by step, we will follow these instructions:
Step 1: Determine the total work
We need to find the least common multiple (LCM) of the days taken by A, B, and C to finish the work.
- A can finish the work in 24 days.
- B can finish the work in 9 days.
- C can finish the work in 12 days.
Calculation of LCM:
- The LCM of 24, 9, and 12 is 72.
Total work = 72 units.
Step 2: Calculate the efficiency of A, B, and C
Now we will calculate how much work each person can do in one day (their efficiency).
- Efficiency of A:
Efficiency of A=72 units24 days=3 units/day
- Efficiency of B:
Efficiency of B=72 units9 days=8 units/day
- Efficiency of C:
Efficiency of C=72 units12 days=6 units/day
Step 3: Calculate the work done by B and C in 3 days
B and C work together for 3 days. We need to find the total work done by both in that time.
- Total efficiency of B and C:
Total efficiency=Efficiency of B+Efficiency of C=8+6=14 units/day
- Work done in 3 days:
Work done=Total efficiency×Time=14×3=42 units
Step 4: Calculate the remaining work
Now we will find out how much work is left after B and C have worked for 3 days.
- Remaining work:
Remaining work=Total work−Work done by B and C=72−42=30 units
Step 5: Calculate the time taken by A to finish the remaining work
Now we need to determine how long it will take A to complete the remaining 30 units of work.
- Time taken by A:
Time=Remaining workEfficiency of A=30 units3 units/day=10 days
Final Answer
The remaining work was done by A in 10 days.
---
We need to find the least common multiple (LCM) of the days taken by A, B, and C to finish the work.
- A can finish the work in 24 days.
- B can finish the work in 9 days.
- C can finish the work in 12 days.
- The LCM of 24, 9, and 12 is 72.
Now we will calculate how much work each person can do in one day (their efficiency).
Efficiency of A=72 units24 days=3 units/day
Efficiency of B=72 units9 days=8 units/day
Efficiency of C=72 units12 days=6 units/day
B and C work together for 3 days. We need to find the total work done by both in that time.
Total efficiency=Efficiency of B+Efficiency of C=8+6=14 units/day
Work done=Total efficiency×Time=14×3=42 units
Now we will find out how much work is left after B and C have worked for 3 days.
Remaining work=Total work−Work done by B and C=72−42=30 units
Now we need to determine how long it will take A to complete the remaining 30 units of work.
Time=Remaining workEfficiency of A=30 units3 units/day=10 days
The remaining work was done by A in 10 days.
Similar Questions
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View Solution
Knowledge Check
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A5 daysB6 daysC10 daysD1012 daysA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A5 daysB6 daysC10 daysD1012 daysA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB9 daysC10 daysD13 days
A can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View Solution