A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in

A

10 days

B

1012days

C

5days

D

6days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow these instructions:

Step 1: Determine the total work
We need to find the least common multiple (LCM) of the days taken by A, B, and C to finish the work.
- A can finish the work in 24 days.
- B can finish the work in 9 days.
- C can finish the work in 12 days.

Calculation of LCM:
- The LCM of 24, 9, and 12 is 72.

Total work = 72 units.

Step 2: Calculate the efficiency of A, B, and C
Now we will calculate how much work each person can do in one day (their efficiency).

- Efficiency of A:
Efficiency of A=72 units24 days=3 units/day

- Efficiency of B:
Efficiency of B=72 units9 days=8 units/day

- Efficiency of C:
Efficiency of C=72 units12 days=6 units/day

Step 3: Calculate the work done by B and C in 3 days
B and C work together for 3 days. We need to find the total work done by both in that time.

- Total efficiency of B and C:
Total efficiency=Efficiency of B+Efficiency of C=8+6=14 units/day

- Work done in 3 days:
Work done=Total efficiency×Time=14×3=42 units

Step 4: Calculate the remaining work
Now we will find out how much work is left after B and C have worked for 3 days.

- Remaining work:
Remaining work=Total workWork done by B and C=7242=30 units

Step 5: Calculate the time taken by A to finish the remaining work
Now we need to determine how long it will take A to complete the remaining 30 units of work.

- Time taken by A:
Time=Remaining workEfficiency of A=30 units3 units/day=10 days

Final Answer
The remaining work was done by A in 10 days.

---

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B9 days
    C10 days
    D13 days