A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then the total number of days need for the completion of the work is: a 4 days b 5 days c 6 days d 9 days
Correct option c 6 daysExplanation: 3 days work of A and B is 3 × 3 =9 units Work left= 12-9=3 unitsB finishes in = 3/1 = 3 daystotal no. of days ⇒ 3+3 =6 days
Related Solutions
A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is
View SolutionA , B तथा C किसी काम को क्रमश : 24 दिन 9 दिन तथा 12 दिनों में कर सकते है B और C साथ काम करना आरभ करते है लेकिन 3 दिन बाद वे काम छोड़ देता है शेष काम A कितने दिनों में पूरा करेगा ?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA can do a piece of work in 24 days, B in 9 days and C in 12 days. B and C start the work together, but leave after 3 days. How many days will A take to complete the remaining work?
View SolutionA, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View SolutionA एक काम को 6 दिनों में तथा B उसी काम को 9 दिनों में कर सकता है दोनों मिलकर उस काम को कितने दिन में पूरा करेंगे ?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A, B and C together can do it in 6 days. In how many days will A and C together complete it?
View SolutionA, B and C can complete a work in 24 days, 9 days and 12 days respectively. B and C start the work but they have to leave it after 3 days. The time taken by A to do the remaining work is
View Solutionकिसी कार्य को A, B तथा c क्रमशः 24 दिन, 9 दिन व 12 दिन में पूरा कर सकते है। B तथा C कार्य प्रारम्भ करते है , परन्तु उन्हें 3 दिन बाद यह कार्य छोड़ना पड़ता है। शेष कार्य को करने में A को लगा समय है
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View SolutionB and C can complete a piece of work in 12 days,C and A can do it in 8 days. All the three can do it in 6 days. A and B together can complete It In (A) 4 days (B) 6 days (C ) 8 days (D) 10 days
View SolutionA can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
View SolutionSome persons can do piece of work in 12 days. Two times the number of such persons will do half of the work in
(A) 9 days (B) 6 days (C) 5 days (D) 3 days
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA can do a piece of work in 12 days. B can do the same work in 8 days and C can do the same job in th time required by both A and B. A and B work together for 3 days. Then C completes the job. How many complete days did C work?
View SolutionA can do 1//6 of a work in 5 days and B can do 2/5 of the work in 8 days. In how many days can both A and B together do the work? (A) 12 days (B) 13 days (C ) 15 days (D) 20 days
View Solution