A B and C can complete a piece of work in 10 12 and 15 days respectively They started the work together. But A left the work before 5 days of its completion B also left the work 2 days after A left. In how many days was the work completed?a 4 daysb 5 daysc 7 daysd 8 days
Correct option c 7 daysExplanation: In these type of questions where a person left few day before the completion of work in that casecalculate the unit of work he would have done if he had not left the work and add there unit in total work and divide by their total work per day. Here A left 5 days before it means. A would have done 30 units and B left 2 days after ‘A’ it means he left 3 days before completion. 3 days × 5 unit/day = 15 unitSo total work they would have completed if all of them had worked till end. Then total work = 60+30+15 = 105 units and their one day work = 6+5+4 = 15
Related Solutions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? b. c. d.
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.
b.
c.
d.
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 24, 30 and 40 days respectively. They started working together but C left the work 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View Solution3 men A, B, C can do a piece of work in 10, 12 and 15 days respectively. If A, B, C started working together, but after 2 days A left the work and after 2 days C also left the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 12, 15 and 18 days respectively. They started working together, but after 2 days A left the work and B left 3 days before the completion of that work. In how many days the whole work was completed?
View SolutionA, B और C किसी काम को क्रमश: 10 , 12 तथा 15 दिन में पूरा कर सकते है A ने काम पूरा होने से 5 दिन पहले काम छोड़ दिया और B ने A के काम छोड़ने के 2 दिन बाद काम छोड़ दिया । समस्त काम पूरा करने के लिए कितने दिनों की आवश्यकता होगी ?
View SolutionA, B and C take 36 days, 54 days and 72 days respectively to finish a piece of work. The three started working together. A left the work 8 days before the end of the work and B left 12 days before the completion of the work. For how many days did C work?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA and B together can complete a piece of work in 30 days. Together they worked for 10 days and B left. The remaining work was completed by A alone in next 30 days. In how many days will B alone complete the work?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View Solution