Question

A B and C can complete a piece of work in 10 12 and 15 days respectively They started the work together. But A left the work before 5 days of its completion B also left the work 2 days after A left. In how many days was the work completed?a 4 daysb 5 daysc 7 daysd 8 days

Text Solution
Verified by Experts

Correct option c 7 daysExplanation: In these type of questions where a person left few day before the completion of work in that casecalculate the unit of work he would have done if he had not left the work and add there unit in total work and divide by their total work per day. Here A left 5 days before it means. A would have done 30 units and B left 2 days after ‘A’ it means he left 3 days before completion. 3 days × 5 unit/day = 15 unitSo total work they would have completed if all of them had worked till end. Then total work = 60+30+15 = 105 units and their one day work = 6+5+4 = 15


Related Solutions