Doubtnut Promotions Sticky

A contractor calculated that he could finish the construction of a road in 40 working days. He knew appointed 32 people and made them work for 6 hours a day for 5 days in a week, the work would finish But he could arrange for only 20 workers. He decided to make them work for 8 hours a day for 6 days a week Will they complete the work in time? If not, how many more days will they take?

Video Solution
|
Answer

Step by step video & image solution for A contractor calculated that he could finish the construction of a road in 40 working days. He knew appointed 32 people and made them work for 6 hours a day for 5 days in a week, the work would finish But he could arrange for only 20 workers. He decided to make them work for 8 hours a day for 6 days a week Will they complete the work in time? If not, how many more days will they take? by Maths experts to help you in doubts & scoring excellent marks in Class 12 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611

    A5511
    B5611
    C6511
    D6611
  • Question 2 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

    A5511
    B5611
    C6511
    D6611
  • Question 3 - Select One

    A can do a work in 12 days when he had worked for 3 days B joined him if they complete the work in 3 more days in how many days can B alone finish the work?

    A6 days
    B12 days
    C4 days
    D8 days