Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

A

3 days

B

4 days

C

4.5 days

D

5.4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we need to determine how long A and B will take to complete the work when they work together for 8 hours a day.

Step 1: Calculate the total work done by A and B

1. Calculate A's work rate:
- A can complete the work in 8 days, working 5 hours a day.
- Total hours A works = 8 days × 5 hours/day = 40 hours.
- Therefore, A's work rate = Total work / Total hours = 1 work unit / 40 hours = 1/40 work units per hour.

2. Calculate B's work rate:
- B can complete the work in 10 days, working 6 hours a day.
- Total hours B works = 10 days × 6 hours/day = 60 hours.
- Therefore, B's work rate = Total work / Total hours = 1 work unit / 60 hours = 1/60 work units per hour.

Step 2: Combine the work rates of A and B

3. Calculate their combined work rate:
- Combined work rate = A's work rate + B's work rate
- Combined work rate = (1/40 + 1/60) work units per hour.

4. Finding a common denominator:
- The least common multiple (LCM) of 40 and 60 is 120.
- Convert the fractions:
- (1/40) = (3/120)
- (1/60) = (2/120)
- Therefore, combined work rate = (3/120 + 2/120) = (5/120) = (1/24) work units per hour.

Step 3: Calculate the time taken to complete the work together

5. Calculate the time taken to complete the work together:
- If A and B work together, they complete 1/24 of the work in 1 hour.
- To complete 1 work unit, the time taken = 1 work unit / (1/24 work units per hour) = 24 hours.

Step 4: Calculate how many days they will take working 8 hours a day

6. Calculate the number of days required:
- If they work 8 hours a day, the number of days required = Total hours / Hours per day = 24 hours / 8 hours/day = 3 days.

Final Answer:
A and B can jointly complete the work in 3 days when working 8 hours a day.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?

    A3 days
    B6 days
    C4 days
    D5 days
  • Question 2 - Select One

    If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45
  • Question 3 - Select One

    P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

    A5511
    B5611
    C6511
    D6611