8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?

A

16

B

20

C

30

D

10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first calculate the volume of the wall that the first set of workers can build, and then use that information to find out how many workers are needed for the second wall.

Step 1: Calculate the volume of the first wall
The volume of a wall can be calculated using the formula:
Volume=Length×Breadth×Height

For the first wall:
- Length = 18 m
- Breadth = 2 m
- Height = 12 m

So, the volume of the first wall is:
Volume=18m×2m×12m=432m3

Step 2: Calculate the total work done by the workers
The total work done by the workers can be calculated in terms of worker-hours.

Given:
- Number of workers = 8
- Hours worked per day = 9
- Days worked = 10

Total work done (in worker-hours) is:
Total Work=Number of Workers×Hours per Day×Days
Total Work=8×9×10=720worker-hours

Step 3: Calculate the work required to build the wall
The work required to build the first wall can be expressed as:
Work Required=Volume of Wall

We know that 720 worker-hours are required to build 432 m³ of wall. Therefore, the work required per cubic meter is:
Work per m3=720worker-hours432m3=720432=53worker-hours/m3

Step 4: Calculate the volume of the second wall
Now, we need to calculate the volume of the second wall:
- Length = 32 m
- Breadth = 3 m
- Height = 9 m

So, the volume of the second wall is:
Volume=32m×3m×9m=864m3

Step 5: Calculate the total work required for the second wall
Using the work per cubic meter calculated earlier, the total work required for the second wall is:
Total Work Required=Volume of Second Wall×Work per m3
Total Work Required=864m3×53worker-hours/m3=1440worker-hours

Step 6: Calculate the number of workers needed
Now we need to find out how many workers are required to complete this work in the given time.

Given:
- Days = 8
- Hours per Day = 6

Total available worker-hours with x workers is:
Total Worker-Hours=x×6×8=48x

Setting this equal to the total work required:
48x=1440

Now, solving for x:
x=144048=30

Final Answer
Thus, 30 workers will be able to build the second wall in the given time.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?

    A60
    B20
    C30
    D35
  • If 17 labourers can dig a ditch 20 m long in 18 days working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 day, each labourer working 9 hours a day? 34 b. 51 c. 68 d. 85

    A51
    B68
    C85
    D34
  • 40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

    A32
    B18
    C36
    D9