A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:10 hours a day


To solve the problem step by step, we can follow these instructions:

Step 1: Calculate the total hours worked in 5 days
The man works 8 hours a day for 5 days. To find the total hours worked, we multiply the number of hours per day by the number of days.

Total hours=Hours per day×Number of days=8hours/day×5days=40hours

Step 2: Determine the daily hours needed to complete the project in 4 days
Now, we need to find out how many hours he must work each day to complete the same project in 4 days. We take the total hours calculated in Step 1 and divide it by the new number of days (4 days).

Hours per day=Total hoursNumber of days=40hours4days=10hours/day

Conclusion
The man must work 10 hours a day to complete the project in 4 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
    यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?

    A6
    B10
    C8
    D12
  • Three pumps working 8 hours a day can empty a tank in 2 day. How many hours a day must 4 pumps work to empty the tank in 1 day.

    A10 hours
    B12 hours
    C8 hours
    DNone of these
  • A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411