A can do a certain work in 12 days and B can do it in 18 days. They worked together for 4 days. The remaining work was completed by C alone in 6 days. If they get Rs 3.240 for the whole work, then the share of C in this amount will be:

A

Rs 1,080

B

Rs 1,440

C

Rs 1,260

D

Rs 1,170

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these calculations:

Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 12 days, so A's work in one day = 112 of the work.
- B can complete the work in 18 days, so B's work in one day = 118 of the work.

Step 2: Find the combined work done by A and B in one day.
- Combined work of A and B in one day = 112+118.
- To add these fractions, find a common denominator. The least common multiple of 12 and 18 is 36.
- Convert the fractions:
- 112=336
- 118=236
- Therefore, combined work = 336+236=536.

Step 3: Calculate the total work done by A and B in 4 days.
- Work done by A and B in 4 days = 4×536=2036=59 of the work.

Step 4: Calculate the remaining work.
- Total work = 1 (whole work).
- Remaining work = 159=49 of the work.

Step 5: Calculate the work done by C.
- C completes the remaining 49 of the work in 6 days.
- Therefore, C's work in one day = 4/96=454=227 of the work.

Step 6: Calculate the total amount and C's share.
- Total payment for the work = Rs. 3240.
- The total work can be considered as 1 unit of work, and the payment can be divided based on the amount of work done.
- Work done by C = 49.
- Total work done = 1 unit (A + B + C).
- C's share = Cs workTotal work×Total payment.
- C's share = 4/91×3240=4×32409=1440.

Final Answer:
C's share in the amount will be Rs. 1440.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

    A10 days
    B9 days
    C12 days
    D15 days
  • A can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?

    ARs. 12,800
    BRs. 12,500
    CRs. 13,200
    DRs. 12,000
  • If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?

    A445 days
    B4 days
    C345 days
    D6 days