A can do a certain work in 12 days and B can do it in 18 days. They worked together for 4 days. The remaining work was completed by C alone in 6 days. If they get Rs 3.240 for the whole work, then the share of C in this amount will be:
Rs 1,080
Rs 1,440
Rs 1,260
Rs 1,170
The correct Answer is:B
To solve the problem step by step, we can follow these calculations:
Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 12 days, so A's work in one day = 112 of the work.
- B can complete the work in 18 days, so B's work in one day = 118 of the work.
Step 2: Find the combined work done by A and B in one day.
- Combined work of A and B in one day = 112+118.
- To add these fractions, find a common denominator. The least common multiple of 12 and 18 is 36.
- Convert the fractions:
- 112=336
- 118=236
- Therefore, combined work = 336+236=536.
Step 3: Calculate the total work done by A and B in 4 days.
- Work done by A and B in 4 days = 4×536=2036=59 of the work.
Step 4: Calculate the remaining work.
- Total work = 1 (whole work).
- Remaining work = 1−59=49 of the work.
Step 5: Calculate the work done by C.
- C completes the remaining 49 of the work in 6 days.
- Therefore, C's work in one day = 4/96=454=227 of the work.
Step 6: Calculate the total amount and C's share.
- Total payment for the work = Rs. 3240.
- The total work can be considered as 1 unit of work, and the payment can be divided based on the amount of work done.
- Work done by C = 49.
- Total work done = 1 unit (A + B + C).
- C's share = C′s workTotal work×Total payment.
- C's share = 4/91×3240=4×32409=1440.
Final Answer:
C's share in the amount will be Rs. 1440.
---
- A can complete the work in 12 days, so A's work in one day = 112 of the work.
- B can complete the work in 18 days, so B's work in one day = 118 of the work.
- Combined work of A and B in one day = 112+118.
- To add these fractions, find a common denominator. The least common multiple of 12 and 18 is 36.
- Convert the fractions:
- 112=336
- 118=236
- Therefore, combined work = 336+236=536.
- Work done by A and B in 4 days = 4×536=2036=59 of the work.
- Total work = 1 (whole work).
- Remaining work = 1−59=49 of the work.
- C completes the remaining 49 of the work in 6 days.
- Therefore, C's work in one day = 4/96=454=227 of the work.
- Total payment for the work = Rs. 3240.
- The total work can be considered as 1 unit of work, and the payment can be divided based on the amount of work done.
- Work done by C = 49.
- Total work done = 1 unit (A + B + C).
- C's share = C′s workTotal work×Total payment.
- C's share = 4/91×3240=4×32409=1440.
C's share in the amount will be Rs. 1440.
Similar Questions
A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
View SolutionA can do a piece of work in 120 days and B can do it in 150 days. The work together for 20 days. Then, B leave and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it, if he works alone?
View Solution
Knowledge Check
A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
A10 daysB9 daysC12 daysD15 daysA can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?
ARs. 12,800BRs. 12,500CRs. 13,200DRs. 12,000If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
A445 daysB4 daysC345 daysD6 days
A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
View SolutionA can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
View SolutionA can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
View Solution