Read the following information carefully to answer the questions.
A,B and C can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days,time taken by C to complete the remaining job is x days.
P,Q and R take (x-28) days, (x-18) days and (x-8) days respectively to complete a job. The three work in a rotation to complete the job with only one person working on a day .Who should start the job so that the job is complete in the least possible time?

A

P

B

Cannot be determined

C

Q

D

Any one of hree

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the efficiencies of A, B, and C, then calculate the remaining work after A and B have worked, and finally find the value of x. After that, we will analyze the work rates of P, Q, and R to determine who should start the job to minimize the total time.

Step 1: Determine the efficiencies of A, B, and C

1. A, B, and C together can complete the work in 16 days.
- Work done by A, B, and C in one day = 116 of the work.

2. B and C together can complete the work in 32 days.
- Work done by B and C in one day = 132 of the work.

3. C can complete the work in 80 days.
- Work done by C in one day = 180 of the work.

Let’s denote:
- Work done by A in one day = A
- Work done by B in one day = B
- Work done by C in one day = C

From the information:
- A+B+C=116
- B+C=132
- C=180

Step 2: Calculate A and B's efficiencies

From B+C=132:
- Substituting C:
B+180=132
B=132180
To subtract these fractions, find a common denominator (which is 160):
B=51602160=3160

Now substituting B back to find A:
A+3160+180=116
Substituting 180=2160:
A+3160+2160=116
A+5160=10160
A=101605160=5160=132

Step 3: Calculate the total work done after A and B have worked

1. A works for 4 days:
- Work done by A in 4 days = 4×132=432=18

2. B works for 12 days:
- Work done by B in 12 days = 12×3160=36160=940

3. Total work done by A and B:
Total work done=18+940
Converting 18 to a denominator of 40:
18=540
Total work done=540+940=1440=720

4. Remaining work:
Remaining work=1720=1320

Step 4: Calculate the time taken by C to complete the remaining work

Since C can do 180 of the work in one day:
- Time taken by C to complete the remaining work:
x=Remaining workC's work rate=1320180=1320×80=52 days

Step 5: Determine the work rates of P, Q, and R

1. P takes x28 days:
P=5228=24 days

2. Q takes x18 days:
Q=5218=34 days

3. R takes x8 days:
R=528=44 days

Step 6: Calculate the work done by P, Q, and R in one day

- Work done by P in one day = 124
- Work done by Q in one day = 134
- Work done by R in one day = 144

Step 7: Determine who should start the job

To minimize the total time, we need to find out who can complete the most work in the least time. The person with the highest efficiency (lowest time) should start.

- P's efficiency: 124
- Q's efficiency: 134
- R's efficiency: 144

Since 124>134>144, P is the most efficient.

Conclusion

P should start the job to complete it in the least possible time.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16
  • A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days
  • A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9