Read the following information carefully to answer the questions.
A,B and C can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days,time taken by C to complete the remaining job is x days.
P,Q and R take (x-28) days, (x-18) days and (x-8) days respectively to complete a job. The three work in a rotation to complete the job with only one person working on a day .Who should start the job so that the job is complete in the least possible time?
P
Cannot be determined
Q
Any one of hree
The correct Answer is:A
To solve the problem step by step, we will first determine the efficiencies of A, B, and C, then calculate the remaining work after A and B have worked, and finally find the value of x. After that, we will analyze the work rates of P, Q, and R to determine who should start the job to minimize the total time.
Step 1: Determine the efficiencies of A, B, and C
1. A, B, and C together can complete the work in 16 days.
- Work done by A, B, and C in one day = 116 of the work.
2. B and C together can complete the work in 32 days.
- Work done by B and C in one day = 132 of the work.
3. C can complete the work in 80 days.
- Work done by C in one day = 180 of the work.
Let’s denote:
- Work done by A in one day = A
- Work done by B in one day = B
- Work done by C in one day = C
From the information:
- A+B+C=116
- B+C=132
- C=180
Step 2: Calculate A and B's efficiencies
From B+C=132:
- Substituting C:
B+180=132
B=132−180
To subtract these fractions, find a common denominator (which is 160):
B=5160−2160=3160
Now substituting B back to find A:
A+3160+180=116
Substituting 180=2160:
A+3160+2160=116
A+5160=10160
A=10160−5160=5160=132
Step 3: Calculate the total work done after A and B have worked
1. A works for 4 days:
- Work done by A in 4 days = 4×132=432=18
2. B works for 12 days:
- Work done by B in 12 days = 12×3160=36160=940
3. Total work done by A and B:
Total work done=18+940
Converting 18 to a denominator of 40:
18=540
Total work done=540+940=1440=720
4. Remaining work:
Remaining work=1−720=1320
Step 4: Calculate the time taken by C to complete the remaining work
Since C can do 180 of the work in one day:
- Time taken by C to complete the remaining work:
x=Remaining workC's work rate=1320180=1320×80=52 days
Step 5: Determine the work rates of P, Q, and R
1. P takes x−28 days:
P=52−28=24 days
2. Q takes x−18 days:
Q=52−18=34 days
3. R takes x−8 days:
R=52−8=44 days
Step 6: Calculate the work done by P, Q, and R in one day
- Work done by P in one day = 124
- Work done by Q in one day = 134
- Work done by R in one day = 144
Step 7: Determine who should start the job
To minimize the total time, we need to find out who can complete the most work in the least time. The person with the highest efficiency (lowest time) should start.
- P's efficiency: 124
- Q's efficiency: 134
- R's efficiency: 144
Since 124>134>144, P is the most efficient.
Conclusion
P should start the job to complete it in the least possible time.
- Work done by A, B, and C in one day = 116 of the work.
2. B and C together can complete the work in 32 days.
- Work done by B and C in one day = 132 of the work.
- Work done by C in one day = 180 of the work.
- Work done by A in one day = A
- Work done by B in one day = B
- Work done by C in one day = C
- A+B+C=116
- B+C=132
- C=180
- Substituting C:
B+180=132
B=132−180
To subtract these fractions, find a common denominator (which is 160):
B=5160−2160=3160
A+3160+180=116
Substituting 180=2160:
A+3160+2160=116
A+5160=10160
A=10160−5160=5160=132
- Work done by A in 4 days = 4×132=432=18
- Work done by B in 12 days = 12×3160=36160=940
Total work done=18+940
Converting 18 to a denominator of 40:
18=540
Total work done=540+940=1440=720
Remaining work=1−720=1320
- Time taken by C to complete the remaining work:
x=Remaining workC's work rate=1320180=1320×80=52 days
P=52−28=24 days
Q=52−18=34 days
R=52−8=44 days
- Work done by Q in one day = 134
- Work done by R in one day = 144
- Q's efficiency: 134
- R's efficiency: 144
Similar Questions
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 daysA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9
A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is
View SolutionIf A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?
View SolutionA and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 days
View Solution