A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is

A

16

B

8

C

12

D

24

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work efficiencies of A, B, and C based on the information provided.

Step 1: Determine the efficiencies of A + B, B + C, and A + B + C

1. A + B can complete the work in 8 days.
- Efficiency of A + B = 1/8 (work done per day)

2. B + C can complete the work in 12 days.
- Efficiency of B + C = 1/12 (work done per day)

3. A + B + C can complete the work in 6 days.
- Efficiency of A + B + C = 1/6 (work done per day)

Step 2: Convert efficiencies to a common base

To find the individual efficiencies, we can use the least common multiple (LCM) of the denominators (8, 12, and 6). The LCM of these numbers is 24.

- Efficiency of A + B:
Efficiency=248=3 (units of work per day)

- Efficiency of B + C:
Efficiency=2412=2 (units of work per day)

- Efficiency of A + B + C:
Efficiency=246=4 (units of work per day)

Step 3: Find the individual efficiencies of A, B, and C

Now we can set up equations based on the efficiencies we calculated:

1. Let the efficiency of A be a, B be b, and C be c.
- From A + B: a+b=3 (1)
- From B + C: b+c=2 (2)
- From A + B + C: a+b+c=4 (3)

Step 4: Solve the equations

From equation (3), we can express c in terms of a and b:
c=4(a+b)=43=1

Now substitute c back into equation (2):
b+1=2b=1

Now substitute b back into equation (1):
a+1=3a=2

Step 5: Summary of efficiencies

- Efficiency of A = 2
- Efficiency of B = 1
- Efficiency of C = 1

Step 6: Find the efficiency of A + C

Now we need to find the efficiency of A + C:
Efficiency of A + C=a+c=2+1=3

Step 7: Calculate the number of days required for A and C to finish the work

The total work is represented by the LCM we calculated earlier, which is 24 units. Therefore, the number of days required for A and C to finish the work is:
Days=Total WorkEfficiency of A + C=243=8 days

Final Answer
The number of days required to finish the work by A and C is 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A4
    B6
    C12
    D9
  • A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16
  • A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days