A,B and C can do a piece of work in 10,12 and 15 days respectively. They started the work together, A leaves 5 days before the completion of the work, B leave 2 days after A left .so the total work lasts for ?
7 days
6 days
12 days
13 days
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C in one day, then set up an equation based on the information given about when they leave the work.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 10 days, so A's work in one day is:
Work by A in 1 day=110 of the work
- B can complete the work in 12 days, so B's work in one day is:
Work by B in 1 day=112 of the work
- C can complete the work in 15 days, so C's work in one day is:
Work by C in 1 day=115 of the work
Step 2: Calculate the total work done by A, B, and C together in one day.
To find the total work done by A, B, and C in one day, we add their individual contributions:
Total work in 1 day=110+112+115
To add these fractions, we need a common denominator. The LCM of 10, 12, and 15 is 60. Thus:
110=660,112=560,115=460
Adding these together:
Total work in 1 day=6+5+460=1560=14 of the work
Step 3: Set up the equation based on the information given.
Let the total time taken to complete the work be x days. According to the problem:
- A works for x−5 days (leaves 5 days before completion).
- B works for x−2 days (leaves 2 days after A).
- C works for all x days.
Now, we can express the total work done in terms of x:
Work done by A=110⋅(x−5)
Work done by B=112⋅(x−2)
Work done by C=115⋅x
Step 4: Combine the work done by A, B, and C and set it equal to 1 (the whole work).
The total work done is:
110(x−5)+112(x−2)+115x=1
Step 5: Solve the equation.
To solve this equation, we first find a common denominator for the fractions, which is 60:
660(x−5)+560(x−2)+460x=1
Multiplying through by 60 to eliminate the denominators:
6(x−5)+5(x−2)+4x=60
Expanding this gives:
6x−30+5x−10+4x=60
Combining like terms:
15x−40=60
Adding 40 to both sides:
15x=100
Dividing by 15:
x=10015=203≈6.67 days
Step 6: Conclusion
The total work lasts for approximately 6.67 days, which can be rounded to 7 days for practical purposes.
Work by A in 1 day=110 of the work
Work by B in 1 day=112 of the work
Work by C in 1 day=115 of the work
Total work in 1 day=110+112+115
110=660,112=560,115=460
Adding these together:
Total work in 1 day=6+5+460=1560=14 of the work
- A works for x−5 days (leaves 5 days before completion).
- B works for x−2 days (leaves 2 days after A).
- C works for all x days.
Work done by A=110⋅(x−5)
Work done by B=112⋅(x−2)
Work done by C=115⋅x
110(x−5)+112(x−2)+115x=1
660(x−5)+560(x−2)+460x=1
6(x−5)+5(x−2)+4x=60
Expanding this gives:
6x−30+5x−10+4x=60
Combining like terms:
15x−40=60
Adding 40 to both sides:
15x=100
Dividing by 15:
x=10015=203≈6.67 days
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?
View Solution
Knowledge Check
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of theseA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
A4B8C12D24
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution