A and B can complete a piece of work in 8 days. B and C in 12 days while C and A in 16 days. They work together for 3 days when A leaves off. In how many days more will B and C finish the remaining work?
112 days
214 days
718 days
412 days
The correct Answer is:A
To solve the problem step by step, let's denote the work done by A, B, and C in one day as A,B, and C respectively.
Step 1: Determine the work rates of A, B, and C
1. A + B can complete the work in 8 days.
- Work done by A and B in one day = 18 of the work.
- Therefore, A+B=18.
2. B + C can complete the work in 12 days.
- Work done by B and C in one day = 112 of the work.
- Therefore, B+C=112.
3. C + A can complete the work in 16 days.
- Work done by C and A in one day = 116 of the work.
- Therefore, C+A=116.
Step 2: Set up equations
We have the following equations:
- A+B=18 (1)
- B+C=112 (2)
- C+A=116 (3)
Step 3: Solve the equations
To find the individual work rates, we can add all three equations:
(A+B)+(B+C)+(C+A)=18+112+116
This simplifies to:
2A+2B+2C=18+112+116
Now, we need to find a common denominator for the right side. The LCM of 8, 12, and 16 is 48.
18=648,112=448,116=348
Adding these fractions:
648+448+348=1348
Thus, we have:
2A+2B+2C=1348
Dividing by 2:
A+B+C=1396
Step 4: Find individual work rates
Now we can express each worker's rate:
1. From (1): A=18−B
2. From (2): C=112−B
3. Substitute into (3):
(112−B)+(18−B)=116
Solving this will give us the values of A, B, and C.
Step 5: Calculate work done in 3 days
After finding A, B, and C, we calculate the total work done by A, B, and C together in 3 days:
Total work in 3 days=3×(A+B+C)
Step 6: Calculate remaining work
Subtract the work done in 3 days from the total work (which is 1 unit):
Remaining work=1−Total work in 3 days
Step 7: Calculate how long B and C will take to finish the remaining work
Now, we know the work done by B and C in one day:
Work done by B and C in one day=B+C=112
Let R be the remaining work. The days required by B and C to finish the remaining work is:
Days=RB+C
Final Answer
After calculating the above steps, we will find the number of days B and C will take to finish the remaining work.
1. A + B can complete the work in 8 days.
- Work done by A and B in one day = 18 of the work.
- Therefore, A+B=18.
- Work done by B and C in one day = 112 of the work.
- Therefore, B+C=112.
- Work done by C and A in one day = 116 of the work.
- Therefore, C+A=116.
We have the following equations:
- A+B=18 (1)
- B+C=112 (2)
- C+A=116 (3)
To find the individual work rates, we can add all three equations:
(A+B)+(B+C)+(C+A)=18+112+116
This simplifies to:
2A+2B+2C=18+112+116
Now, we need to find a common denominator for the right side. The LCM of 8, 12, and 16 is 48.
18=648,112=448,116=348
Adding these fractions:
648+448+348=1348
Thus, we have:
2A+2B+2C=1348
Dividing by 2:
A+B+C=1396
Now we can express each worker's rate:
1. From (1): A=18−B
2. From (2): C=112−B
3. Substitute into (3):
(112−B)+(18−B)=116
Solving this will give us the values of A, B, and C.
After finding A, B, and C, we calculate the total work done by A, B, and C together in 3 days:
Total work in 3 days=3×(A+B+C)
Subtract the work done in 3 days from the total work (which is 1 unit):
Remaining work=1−Total work in 3 days
Now, we know the work done by B and C in one day:
Work done by B and C in one day=B+C=112
Let R be the remaining work. The days required by B and C to finish the remaining work is:
Days=RB+C
After calculating the above steps, we will find the number of days B and C will take to finish the remaining work.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View Solution
Knowledge Check
A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?
A18 daysB24 daysC30 daysD36 daysA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
A18 daysB24 daysC30 daysD36 days
A and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?
View SolutionA and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View Solution