A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?

A

18 days

B

24 days

C

30 days

D

36 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will determine the work efficiencies of A, B, and C based on the information provided and then calculate how long A will take to finish the remaining work after B and C leave.

Step 1: Determine the work efficiencies of A, B, and C

1. A and B can complete the work in 30 days.
- Work done by A and B in one day = 1/30 of the work.

2. B and C can complete the work in 24 days.
- Work done by B and C in one day = 1/24 of the work.

3. C and A can complete the work in 20 days.
- Work done by C and A in one day = 1/20 of the work.

Step 2: Set up equations based on the efficiencies

Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c

From the above information, we can set up the following equations:
1. a+b=130 (1)
2. b+c=124 (2)
3. c+a=120 (3)

Step 3: Solve the equations

To find the individual efficiencies, we can add all three equations:

(a+b)+(b+c)+(c+a)=130+124+120

This simplifies to:

2a+2b+2c=130+124+120

Now, calculate the right side using LCM:

- LCM of 30, 24, and 20 is 120.
- Convert each fraction:
- 130=4120
- 124=5120
- 120=6120

Adding these gives:

4+5+6120=15120=18

Thus, we have:

2(a+b+c)=18

Dividing by 2:

a+b+c=116

Step 4: Find individual efficiencies

Now we can find the individual efficiencies:

1. From equation (1): b=130a
2. Substitute b in equation (2):
- 130a+c=124
- Rearranging gives c=124130+a

3. Substitute c in equation (3):
- a+(124130+a)=120
- Solve for a.

After solving, we find:
- a=140
- b=160
- c=130

Step 5: Calculate the combined efficiency

Now, we can find the combined efficiency of A, B, and C:

a+b+c=140+160+130=3+2+4120=9120=340

Step 6: Work done in 10 days

If they work together for 10 days:

Work done in 10 days=10×340=3040=34

Step 7: Remaining work

Total work = 1 (whole work), so remaining work:

134=14

Step 8: A's efficiency

We already calculated A's efficiency as 140.

Step 9: Time taken by A to finish the remaining work

To find how many days A will take to finish the remaining 14:

Time=Remaining WorkA's Efficiency=14140=404=10 days

Final Answer

A will take 10 more days to finish the work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b.  24 days c. 30 days d. 36 days

    A18 days
    B24 days
    C30 days
    D36 days
  • A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?

    A16 days
    B15 days
    C18 days
    D20 days
  • A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

    A9 days
    B11 days
    C15 days
    D20 days