A group of workers could complete a piece of work in 84 days. If there were 6 more workers, it would have taken 12 days less to finish the same piece of work. What was the actual strength of workers ?
42
36
48
32
The correct Answer is:B
To solve the problem step by step, we can follow these steps:
Step 1: Define the Variables
Let the actual number of workers be x.
Step 2: Calculate the Total Work
The total work done can be expressed in terms of the number of workers and the number of days they work. If x workers can complete the work in 84 days, then the total work W can be expressed as:
W=x×84
Step 3: Set Up the Equation for Increased Workers
If there are 6 more workers, the total number of workers becomes x+6. According to the problem, with these additional workers, the work can be completed in 12 days less, which means it would take 72 days (since 84−12=72). The total work can also be expressed as:
W=(x+6)×72
Step 4: Equate the Two Expressions for Work
Since both expressions represent the same total work, we can set them equal to each other:
x×84=(x+6)×72
Step 5: Expand and Simplify the Equation
Expanding the right side:
84x=72x+432
Step 6: Rearrange the Equation
Now, we can rearrange the equation to isolate x:
84x−72x=432
12x=432
Step 7: Solve for x
Dividing both sides by 12 gives:
x=43212=36
Conclusion
The actual strength of the workers is 36.
Let the actual number of workers be x.
The total work done can be expressed in terms of the number of workers and the number of days they work. If x workers can complete the work in 84 days, then the total work W can be expressed as:
W=x×84
If there are 6 more workers, the total number of workers becomes x+6. According to the problem, with these additional workers, the work can be completed in 12 days less, which means it would take 72 days (since 84−12=72). The total work can also be expressed as:
W=(x+6)×72
Since both expressions represent the same total work, we can set them equal to each other:
x×84=(x+6)×72
Expanding the right side:
84x=72x+432
Now, we can rearrange the equation to isolate x:
84x−72x=432
12x=432
Dividing both sides by 12 gives:
x=43212=36
The actual strength of the workers is 36.
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA group of workers promise to complete a piece of work in 10 days, but five of them do not report for work. If it took the remaining workers 12 days to complete the work, then the number of workers originally hired was 15 b. 25 c. 30 d. 45
View Solution
Knowledge Check
A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less. What was the actual strength of workers?
A30 workersB40 workersC42 workersD36 workersA group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?
A30 workersB40 workersC42 workersD36 workersA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36
a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
View Solution