A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?

A

18

B

27

C

26.67

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we need to determine how many days it will take for A and B to complete the project together, given that A quits 10 days before the project is finished.

Step 1: Determine the work rates of A and B
- A can complete the project in 20 days. Therefore, A's work rate is:
Work rate of A=120 of the project per day

- B can complete the project in 30 days. Therefore, B's work rate is:
Work rate of B=130 of the project per day

Step 2: Combine their work rates
When A and B work together, their combined work rate is:
Combined work rate=120+130
To add these fractions, we need a common denominator, which is 60:
120=360,130=260
Thus,
Combined work rate=360+260=560=112
This means together, A and B can complete 112 of the project in one day.

Step 3: Set up the equation for total work
Let x be the total number of days the project takes to complete. Since A quits 10 days before the project is completed, A works for x10 days, and B works for all x days.

The work done by A in x10 days is:
Work done by A=120×(x10)
The work done by B in x days is:
Work done by B=130×x

Step 4: Write the equation for total work
The total work done by A and B together must equal 1 (the whole project):
120(x10)+130x=1

Step 5: Solve the equation
To solve the equation, we first find a common denominator for the fractions, which is 60:
360(x10)+260x=1
Multiplying through by 60 to eliminate the fractions:
3(x10)+2x=60
Expanding the equation:
3x30+2x=60
Combining like terms:
5x30=60
Adding 30 to both sides:
5x=90
Dividing by 5:
x=18

Final Answer
The project will be completed in 18 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

    A1305 days
    B1067 days
    C1147 days
    D1207 days
  • P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

    A9 days
    B14 days
    C12 days
    D18 days
  • A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days