A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
18
27
26.67
16
The correct Answer is:A
To solve the problem step by step, we need to determine how many days it will take for A and B to complete the project together, given that A quits 10 days before the project is finished.
Step 1: Determine the work rates of A and B
- A can complete the project in 20 days. Therefore, A's work rate is:
Work rate of A=120 of the project per day
- B can complete the project in 30 days. Therefore, B's work rate is:
Work rate of B=130 of the project per day
Step 2: Combine their work rates
When A and B work together, their combined work rate is:
Combined work rate=120+130
To add these fractions, we need a common denominator, which is 60:
120=360,130=260
Thus,
Combined work rate=360+260=560=112
This means together, A and B can complete 112 of the project in one day.
Step 3: Set up the equation for total work
Let x be the total number of days the project takes to complete. Since A quits 10 days before the project is completed, A works for x−10 days, and B works for all x days.
The work done by A in x−10 days is:
Work done by A=120×(x−10)
The work done by B in x days is:
Work done by B=130×x
Step 4: Write the equation for total work
The total work done by A and B together must equal 1 (the whole project):
120(x−10)+130x=1
Step 5: Solve the equation
To solve the equation, we first find a common denominator for the fractions, which is 60:
360(x−10)+260x=1
Multiplying through by 60 to eliminate the fractions:
3(x−10)+2x=60
Expanding the equation:
3x−30+2x=60
Combining like terms:
5x−30=60
Adding 30 to both sides:
5x=90
Dividing by 5:
x=18
Final Answer
The project will be completed in 18 days.
---
- A can complete the project in 20 days. Therefore, A's work rate is:
Work rate of A=120 of the project per day
- B can complete the project in 30 days. Therefore, B's work rate is:
Work rate of B=130 of the project per day
When A and B work together, their combined work rate is:
Combined work rate=120+130
To add these fractions, we need a common denominator, which is 60:
120=360,130=260
Thus,
Combined work rate=360+260=560=112
This means together, A and B can complete 112 of the project in one day.
Let x be the total number of days the project takes to complete. Since A quits 10 days before the project is completed, A works for x−10 days, and B works for all x days.
Work done by A=120×(x−10)
The work done by B in x days is:
Work done by B=130×x
The total work done by A and B together must equal 1 (the whole project):
120(x−10)+130x=1
To solve the equation, we first find a common denominator for the fractions, which is 60:
360(x−10)+260x=1
Multiplying through by 60 to eliminate the fractions:
3(x−10)+2x=60
Expanding the equation:
3x−30+2x=60
Combining like terms:
5x−30=60
Adding 30 to both sides:
5x=90
Dividing by 5:
x=18
The project will be completed in 18 days.
Similar Questions
If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View Solution
Knowledge Check
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A1305 daysB1067 daysC1147 daysD1207 daysP alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
A9 daysB14 daysC12 daysD18 daysA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days
A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionK alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View Solution