A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete it in 4 days ?
The correct Answer is:10 hours a day
To solve the problem step by step, we can follow these instructions:
Step 1: Calculate Total Hours Needed for the Project
The man works 8 hours a day for 5 days. To find the total hours needed to complete the project, we multiply the number of hours he works each day by the number of days he works.
Total Hours=Hours per Day×Number of Days=8hours/day×5days=40hours
Step 2: Determine the New Daily Hours Required
Now, we need to find out how many hours he must work each day to complete the same project in 4 days. We know that the total hours required to complete the project is 40 hours.
Let x be the number of hours he needs to work each day. Since he wants to complete the work in 4 days, we can set up the equation:
Total Hours=Hours per Day×Number of Days
40hours=xhours/day×4days
Step 3: Solve for x
To find x, we can rearrange the equation:
x=40hours4days=10hours/day
Conclusion
Therefore, the man must work 10 hours a day to complete the project in 4 days.
---
The man works 8 hours a day for 5 days. To find the total hours needed to complete the project, we multiply the number of hours he works each day by the number of days he works.
Now, we need to find out how many hours he must work each day to complete the same project in 4 days. We know that the total hours required to complete the project is 40 hours.
40hours=xhours/day×4days
To find x, we can rearrange the equation:
Therefore, the man must work 10 hours a day to complete the project in 4 days.
Similar Questions
Working 8 hours a day, Ashu can a book in 18 days. How many hours a day should he work so as to finish the work in 12 days?
View Solution90 men can complete a work in 24 days working 8 hours a day. How many men are working 8 hours a day. How many men are required to complete the same work in 18 days working 712 hours a day ?
View Solution
Knowledge Check
- Question 1 - Select One
How many days did Gandhi take to complete the Dandi March?
A15B20C25D30
If 10 men take 6 days to construct a garage, how many more men are needed if the garage is to be constructed in 5 days ?
View SolutionTen men, working for 6 days of 10 hours each, finish 521 of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days ?
View SolutionTwelve typists, all working with same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days ?
View SolutionIf 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?
View SolutionIn order to complete a work in 28 days, 60 men are required. How Mny men will be required if the same work is to be completed in 40 days ?
View SolutionRakesh can do piece of work in 20 days. How much work can be do in 4 days?
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution