If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?
The correct Answer is:25 days
To solve the problem step by step, we can use the concept of direct variation. The number of men and the number of days taken to complete the work are inversely proportional. This means that as the number of men increases, the number of days taken decreases.
1. Understand the Given Information:
- 15 men can complete the work in 30 days.
2. Calculate the Total Work in Man-Days:
- Total work can be calculated as the product of the number of men and the number of days they work.
- Total work = Number of men × Number of days = 15 men × 30 days = 450 man-days.
3. Determine the Work Done by One Man:
- Since 15 men take 30 days to complete the work, we can find out how many days one man would take to complete the same work alone.
- One man would take 450 days to complete the work (since he would have to do the work of all 15 men).
4. Calculate the Time Taken by 18 Men:
- Now, if we have 18 men working, we can find out how many days they would take to complete the same amount of work.
- Since the work is constant, we can use the formula:
Days taken by 18 men=Total work in man-daysNumber of men=450 man-days18 men.
- Performing the calculation:
45018=25 days.
5. Conclusion:
- Therefore, 18 men will complete the work in 25 days.
Final Answer:
18 men will complete the work in 25 days.
---
- 15 men can complete the work in 30 days.
- Total work can be calculated as the product of the number of men and the number of days they work.
- Total work = Number of men × Number of days = 15 men × 30 days = 450 man-days.
- Since 15 men take 30 days to complete the work, we can find out how many days one man would take to complete the same work alone.
- One man would take 450 days to complete the work (since he would have to do the work of all 15 men).
- Now, if we have 18 men working, we can find out how many days they would take to complete the same amount of work.
- Since the work is constant, we can use the formula:
Days taken by 18 men=Total work in man-daysNumber of men=450 man-days18 men.
- Performing the calculation:
45018=25 days.
- Therefore, 18 men will complete the work in 25 days.
18 men will complete the work in 25 days.
Topper's Solved these Questions
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (D)13videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (E)19videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (B)11videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DATA HANDLING EXERCISE - EXERCISE 22 (B)10videos
DATA HANDLING
- BOOK - ICSECHAPTER - EXPONENTS (POWERS) EXERCISE - EXERCISE 2(B)50videos
EXPONENTS (POWERS)
Similar Questions
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work ?
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View SolutionIf 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?
View SolutionB takes 16 days less than A to do a certain piece of work. If both working together can complete the work in 15 days, in how many days will B alone complete the work ?
View Solution72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?
View Solution2 men or 3 women can do a piece of work in 45 days. Find, in how many days will 6 men and 1 woman be able to complete the same work ?
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View Solution5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution