72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:60 days


To solve the problem step by step, we will use the concept of inverse variation.

Step 1: Understand the relationship
We know that the amount of work done is constant. Therefore, if the number of men increases, the number of days required to complete the work decreases, and vice versa. This is an example of inverse variation.

Step 2: Set up the equation
Let the number of days required by 30 men to complete the work be x. We can set up the relationship as follows:
(Number of men)×(Number of days)=constant
From the problem, we know:
72 men×25 days=30 men×x days

Step 3: Substitute the known values
Substituting the known values into the equation gives us:
72×25=30×x

Step 4: Calculate the left side
Now calculate 72×25:
72×25=1800
So, we have:
1800=30×x

Step 5: Solve for x
To find x, divide both sides of the equation by 30:
x=180030

Step 6: Perform the division
Now, perform the division:
x=60

Conclusion
Thus, the number of days required by 30 men to complete the same work is 60 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions