K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?

A

352 days

B

252 days

C

552 days

D

452 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will follow these steps:

Step 1: Determine the work done by K and M in one day.
- K can complete the work in 20 days, so K's work in one day = 1/20 of the work.
- M can complete the work in 30 days, so M's work in one day = 1/30 of the work.

Step 2: Calculate the combined work done by K and M in one day.
- Combined work done by K and M in one day = (1/20 + 1/30).
- To add these fractions, we need a common denominator. The LCM of 20 and 30 is 60.
- K's work in one day = 3/60 and M's work in one day = 2/60.
- Therefore, combined work = (3/60 + 2/60) = 5/60 = 1/12 of the work.

Step 3: Calculate the work done by K and M together in the first 5 days.
- Work done in 5 days = 5 * (1/12) = 5/12 of the work.

Step 4: Determine the remaining work after 5 days.
- Total work = 1 (whole work).
- Remaining work = 1 - 5/12 = 7/12 of the work.

Step 5: Calculate how long it will take M to complete the remaining work.
- M's work in one day = 1/30 of the work.
- To find the time taken by M to complete the remaining work (7/12), we use the formula:
Time=Remaining workM's work in one day=7/121/30
- This simplifies to:
Time=712×30=21012=17.5 days

Final Answer:
M will complete the remaining work in 17.5 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

    A9 days
    B14 days
    C12 days
    D18 days
  • Question 2 - Select One

    F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

    A1305 days
    B1067 days
    C1147 days
    D1207 days
  • Question 3 - Select One

    C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

    A6 days
    B12 days
    C15 days
    D8 days