A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?
24
25
27
30
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C in one day and then calculate the total work completed when they work together, considering the days they leave early.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 36 days, so the work done by A in one day is:
Work done by A in one day=136
- B can complete the work in 54 days, so the work done by B in one day is:
Work done by B in one day=154
- C can complete the work in 72 days, so the work done by C in one day is:
Work done by C in one day=172
Step 2: Find the total work done by A, B, and C together in one day.
To find the total work done by A, B, and C in one day, we add their individual work rates:
Total work done in one day=136+154+172
To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 36, 54, and 72 is 216.
Now, we convert each fraction:
- 136=6216
- 154=4216
- 172=3216
Thus,
Total work done in one day=6+4+3216=13216
Step 3: Set up the equation based on the work done.
Let X be the total number of days taken to complete the work.
- A works for X−8 days (leaves 8 days before completion).
- B works for X−12 days (leaves 12 days before completion).
- C works for X days.
The work done by each person can be expressed as:
- Work done by A: 6216×(X−8)
- Work done by B: 4216×(X−12)
- Work done by C: 3216×X
Step 4: Write the total work equation.
The total work done by A, B, and C together must equal 1 (the whole work):
6216(X−8)+4216(X−12)+3216X=1
Step 5: Simplify the equation.
Multiplying through by 216 to eliminate the denominator:
6(X−8)+4(X−12)+3X=216
Expanding the equation:
6X−48+4X−48+3X=216
Combining like terms:
(6X+4X+3X)−96=216
13X−96=216
Step 6: Solve for X.
Adding 96 to both sides:
13X=216+96
13X=312
Dividing by 13:
X=31213=24
Conclusion
The total number of days taken to complete the work is 24 days.
Work done by A in one day=136
Work done by B in one day=154
Work done by C in one day=172
Total work done in one day=136+154+172
- 136=6216
- 154=4216
- 172=3216
Total work done in one day=6+4+3216=13216
- B works for X−12 days (leaves 12 days before completion).
- C works for X days.
- Work done by A: 6216×(X−8)
- Work done by B: 4216×(X−12)
- Work done by C: 3216×X
6216(X−8)+4216(X−12)+3216X=1
6(X−8)+4(X−12)+3X=216
6X−48+4X−48+3X=216
(6X+4X+3X)−96=216
13X−96=216
13X=216+96
13X=312
X=31213=24
Similar Questions
A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?
View SolutionA, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these - Question 2 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these - Question 3 - Select One
A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View SolutionA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution