A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

A

24

B

25

C

27

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the work done by A, B, and C in one day and then calculate the total work completed when they work together, considering the days they leave early.

Step 1: Determine the work done by A, B, and C in one day.

- A can complete the work in 36 days, so the work done by A in one day is:
Work done by A in one day=136

- B can complete the work in 54 days, so the work done by B in one day is:
Work done by B in one day=154

- C can complete the work in 72 days, so the work done by C in one day is:
Work done by C in one day=172

Step 2: Find the total work done by A, B, and C together in one day.

To find the total work done by A, B, and C in one day, we add their individual work rates:
Total work done in one day=136+154+172

To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 36, 54, and 72 is 216.

Now, we convert each fraction:
- 136=6216
- 154=4216
- 172=3216

Thus,
Total work done in one day=6+4+3216=13216

Step 3: Set up the equation based on the work done.

Let X be the total number of days taken to complete the work.

- A works for X8 days (leaves 8 days before completion).
- B works for X12 days (leaves 12 days before completion).
- C works for X days.

The work done by each person can be expressed as:
- Work done by A: 6216×(X8)
- Work done by B: 4216×(X12)
- Work done by C: 3216×X

Step 4: Write the total work equation.

The total work done by A, B, and C together must equal 1 (the whole work):
6216(X8)+4216(X12)+3216X=1

Step 5: Simplify the equation.

Multiplying through by 216 to eliminate the denominator:
6(X8)+4(X12)+3X=216

Expanding the equation:
6X48+4X48+3X=216

Combining like terms:
(6X+4X+3X)96=216
13X96=216

Step 6: Solve for X.

Adding 96 to both sides:
13X=216+96
13X=312

Dividing by 13:
X=31213=24

Conclusion

The total number of days taken to complete the work is 24 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 2 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9