A certain job was assigned to a group of men to do it in 24 days. But 14 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was
A)32
B)66
C)36
D)56
The correct Answer is:D
Step by step video, text & image solution for A certain job was assigned to a group of men to do it in 24 days. But 14 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
View SolutionA group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
View Solution
Knowledge Check
A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View SolutionA group of men deaded to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
View SolutionIf 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution