Doubtnut Promotions Sticky

Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

A

10

B

15

C

12

D

14

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18
  • Question 1 - Select One

    Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?

    A10
    B21
    C15
    D18
  • Question 1 - Select One

    A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

    A20
    B25
    C30
    D35
  • Question 1 - Select One

    A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 1 - Select One

    Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?

    A55
    B62
    C56
    D60
  • Question 1 - Select One

    If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in :

    A5 days
    B40 days
    C10 days
    D20 days
  • Question 1 - Select One

    If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?

    A114
    B712
    C184
    D172

Similar Questions