Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
A
10
B
15
C
12
D
14
Video Solution
Text Solution
The correct Answer is:C
|
Answer
Step by step video, text & image solution for Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Knowledge Check
- Question 1 - Select One
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A24B20C16D18 - Question 1 - Select One
Some mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
A10B21C15D18 - Question 1 - Select One
A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?
A20B25C30D35 - Question 1 - Select One
A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40 - Question 1 - Select One
A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
A32B36C42D40 - Question 1 - Select One
Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
A55B62C56D60 - Question 1 - Select One
If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in :
A5 daysB40 daysC10 daysD20 days - Question 1 - Select One
If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
A114B712C184D172
Similar Questions
A can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionP and Q can do a job in 2 days, Q and R can do it in 4 days, and P and R in 12/5 days. What is the number of days required for P alone to do the job?
View Solution