A and B can complete a work in 20 days. B and C can complete the same work in 30 days. C and A can complete the same work in 40 days. In how many days they working together to complete the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:18613 days


To solve the problem step by step, we will first determine the individual work rates of A, B, and C based on the information given.

Step 1: Determine the work rates of A, B, and C

1. Work done by A and B together:
- A and B can complete the work in 20 days.
- Therefore, their combined work rate is 120 of the work per day.

2. Work done by B and C together:
- B and C can complete the work in 30 days.
- Therefore, their combined work rate is 130 of the work per day.

3. Work done by C and A together:
- C and A can complete the work in 40 days.
- Therefore, their combined work rate is 140 of the work per day.

Step 2: Set up equations based on the work rates

Let:
- The work rate of A = a
- The work rate of B = b
- The work rate of C = c

From the above information, we can set up the following equations:
1. a+b=120 (Equation 1)
2. b+c=130 (Equation 2)
3. c+a=140 (Equation 3)

Step 3: Solve the equations

To find the individual work rates, we can add all three equations together:

(a+b)+(b+c)+(c+a)=120+130+140

This simplifies to:

2a+2b+2c=120+130+140

Step 4: Find a common denominator

The least common multiple of 20, 30, and 40 is 120. We can convert each fraction:

120=6120,130=4120,140=3120

Adding these fractions gives:

6120+4120+3120=13120

Step 5: Substitute back into the equation

Now we have:

2(a+b+c)=13120

Dividing by 2:

a+b+c=13240

Step 6: Find the total work rate when A, B, and C work together

The combined work rate of A, B, and C is 13240 of the work per day.

Step 7: Calculate the time taken to complete the work together

To find the number of days they will take to complete the work together, we take the reciprocal of their combined work rate:

Time=113240=2401318.46 days

Final Answer

A, B, and C together can complete the work in approximately 18.46 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    A120 days
    B118 days
    C115 days
    D110 days
  • C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

    A6 days
    B12 days
    C15 days
    D8 days
  • A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days