Shivam alone and Deepak alone can finish a task in 6 hours and 10 hours respectively. Find the time taken by both of them together to do twice of the work?

A

8 hr

B

712 hr

C

734 hr

D

6 hr

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will find the time taken by Shivam and Deepak together to complete twice the work.

Step 1: Determine the individual work rates of Shivam and Deepak.
- Shivam can complete the task in 6 hours. Therefore, his work rate is:
Shivam's work rate=1 task6 hours=16 tasks per hour
- Deepak can complete the task in 10 hours. Therefore, his work rate is:
Deepak's work rate=1 task10 hours=110 tasks per hour

Step 2: Calculate the combined work rate of Shivam and Deepak.
- To find their combined work rate, we add their individual work rates:
Combined work rate=Shivam's work rate+Deepak's work rate=16+110
- To add these fractions, we need a common denominator. The least common multiple of 6 and 10 is 30:
16=530and110=330
- Thus,
Combined work rate=530+330=830=415 tasks per hour

Step 3: Calculate the total work for twice the task.
- Since we need to complete twice the work, we multiply the work of one task by 2:
Total work=2 tasks

Step 4: Calculate the time taken to complete twice the work.
- To find the time taken to complete 2 tasks at the combined work rate, we use the formula:
Time=Total workCombined work rate=2 tasks415 tasks per hour
- This simplifies to:
Time=2×154=304=7.5 hours

Final Answer:
The time taken by both Shivam and Deepak together to do twice the work is 7.5 hours.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 5 hours, B in 9 hours and C in 15 hours. If C could work with them for 1 hour only the time taken by A and B together to complete the work is…

    A2 hours
    B3 hours
    C312 hours
    D4 hours
  • X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?

    A45
    B50
    C60
    D30
  • A and B can do a piece of work in 6 days and A alone can do it in 9 days. In how many days can B alone do it?

    A18 days
    B15 days
    C12 days
    D712 days