The ratio of time taken by A, B & C to complete work alone is 4 : 6 : 3 respectively. If all three together complete the work in 8 days, then find in how many days A alone complete three - fourth of the same work?
12
30
15
18
To solve the problem step by step, we will follow these calculations:
Step 1: Understand the ratio of time taken by A, B, and C
The ratio of the time taken by A, B, and C to complete the work alone is given as 4:6:3.
Step 2: Assign variables to the time taken
Let the time taken by A be 4x, by B be 6x, and by C be 3x.
Step 3: Calculate the total work done by A, B, and C together
The total work done by A, B, and C in one day can be calculated as the sum of their efficiencies. The efficiency is the reciprocal of the time taken:
- Efficiency of A = 14x
- Efficiency of B = 16x
- Efficiency of C = 13x
The total efficiency of A, B, and C together is:
Total efficiency=14x+16x+13x
Step 4: Find a common denominator and simplify
The common denominator for 4x, 6x, and 3x is 12x. Thus, we can rewrite the efficiencies:
Total efficiency=312x+212x+412x=3+2+412x=912x=34x
Step 5: Calculate the total work done in 8 days
If A, B, and C together complete the work in 8 days, then the total work W can be calculated as:
W=Total efficiency×Number of days=34x×8=244x=6x
Step 6: Set the total work equal to the work done by A alone
From the previous steps, we know that the total work W is also equal to 24x (since 4x+6x+3x=24x). Thus, we can equate:
6x=24x
Step 7: Solve for x
Multiplying both sides by x:
6=24x2
x2=624=14
x=12
Step 8: Calculate the efficiency of A
Now substituting x back into the time taken by A:
Time taken by A=4x=4×12=2 days
Thus, the efficiency of A is:
Efficiency of A=12 work/day
Step 9: Calculate the amount of work for three-fourths of the total work
The total work W is 24x:
W=24×12=12 units of work
Three-fourths of the work is:
34×12=9 units of work
Step 10: Calculate the time taken by A to complete three-fourths of the work
Using the efficiency of A:
Time taken by A=WorkEfficiency=912=9×2=18 days
Final Answer
A alone can complete three-fourths of the work in 18 days.
The ratio of the time taken by A, B, and C to complete the work alone is given as 4:6:3.
Let the time taken by A be 4x, by B be 6x, and by C be 3x.
The total work done by A, B, and C in one day can be calculated as the sum of their efficiencies. The efficiency is the reciprocal of the time taken:
- Efficiency of A = 14x
- Efficiency of B = 16x
- Efficiency of C = 13x
Total efficiency=14x+16x+13x
The common denominator for 4x, 6x, and 3x is 12x. Thus, we can rewrite the efficiencies:
Total efficiency=312x+212x+412x=3+2+412x=912x=34x
If A, B, and C together complete the work in 8 days, then the total work W can be calculated as:
W=Total efficiency×Number of days=34x×8=244x=6x
From the previous steps, we know that the total work W is also equal to 24x (since 4x+6x+3x=24x). Thus, we can equate:
6x=24x
Multiplying both sides by x:
6=24x2
x2=624=14
x=12
Now substituting x back into the time taken by A:
Time taken by A=4x=4×12=2 days
Thus, the efficiency of A is:
Efficiency of A=12 work/day
The total work W is 24x:
W=24×12=12 units of work
Three-fourths of the work is:
34×12=9 units of work
Using the efficiency of A:
Time taken by A=WorkEfficiency=912=9×2=18 days
A alone can complete three-fourths of the work in 18 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 daysIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A96 daysB128 daysC64 daysD118 daysP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
A48 daysB42 daysC45 daysD51 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionThe capacities of A,B and C to complete a piece of work is 1:2:3. By working together, the thre of them can complete the work in 24 days. In how many days can C alone complete it ?
View SolutionA work is alone by A and B in 4 days while A alone completes the job in 12 days, then in how many days will B alone complete ?
View SolutionAnil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View Solution