10 men working 6 h a day can complete a work in 18 days. How many hours per day must 15 men work to complete the same work in 12 days.

A

6

B

10

C

12

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the relationship between the number of men, the number of days, the number of hours worked per day, and the efficiency of work done.

Step 1: Determine the total work done in man-hours.
The total work done can be calculated using the formula:
Total Work=Number of Men×Number of Days×Number of Hours per Day

For the first scenario:
- Number of Men (P1) = 10
- Number of Days (D1) = 18
- Number of Hours per Day (H1) = 6

Calculating the total work:
Total Work=10×18×6=1080 man-hours

Step 2: Set up the equation for the second scenario.
In the second scenario, we need to find out how many hours (H2) 15 men must work to complete the same work in 12 days.

For the second scenario:
- Number of Men (P2) = 15
- Number of Days (D2) = 12
- Number of Hours per Day (H2) = ?

Using the same total work formula:
Total Work=15×12×H2

Step 3: Equate the total work from both scenarios.
Since the total work done is the same in both scenarios, we can set the equations equal to each other:
10×18×6=15×12×H2

Substituting the total work calculated:
1080=15×12×H2

Step 4: Solve for H2.
First, calculate 15×12:
15×12=180

Now, substitute this back into the equation:
1080=180×H2

To find H2, divide both sides by 180:
H2=1080180=6

Conclusion:
Thus, the number of hours per day that 15 men must work to complete the same work in 12 days is 6 hours.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45
  • If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours
  • If 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
    यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?

    A9
    B18
    C16
    D12