10 men working 6 h a day can complete a work in 18 days. How many hours per day must 15 men work to complete the same work in 12 days.
6
10
12
none of these
The correct Answer is:A
To solve the problem step by step, we will use the relationship between the number of men, the number of days, the number of hours worked per day, and the efficiency of work done.
Step 1: Determine the total work done in man-hours.
The total work done can be calculated using the formula:
Total Work=Number of Men×Number of Days×Number of Hours per Day
For the first scenario:
- Number of Men (P1) = 10
- Number of Days (D1) = 18
- Number of Hours per Day (H1) = 6
Calculating the total work:
Total Work=10×18×6=1080 man-hours
Step 2: Set up the equation for the second scenario.
In the second scenario, we need to find out how many hours (H2) 15 men must work to complete the same work in 12 days.
For the second scenario:
- Number of Men (P2) = 15
- Number of Days (D2) = 12
- Number of Hours per Day (H2) = ?
Using the same total work formula:
Total Work=15×12×H2
Step 3: Equate the total work from both scenarios.
Since the total work done is the same in both scenarios, we can set the equations equal to each other:
10×18×6=15×12×H2
Substituting the total work calculated:
1080=15×12×H2
Step 4: Solve for H2.
First, calculate 15×12:
15×12=180
Now, substitute this back into the equation:
1080=180×H2
To find H2, divide both sides by 180:
H2=1080180=6
Conclusion:
Thus, the number of hours per day that 15 men must work to complete the same work in 12 days is 6 hours.
The total work done can be calculated using the formula:
Total Work=Number of Men×Number of Days×Number of Hours per Day
- Number of Men (P1) = 10
- Number of Days (D1) = 18
- Number of Hours per Day (H1) = 6
Total Work=10×18×6=1080 man-hours
In the second scenario, we need to find out how many hours (H2) 15 men must work to complete the same work in 12 days.
- Number of Men (P2) = 15
- Number of Days (D2) = 12
- Number of Hours per Day (H2) = ?
Total Work=15×12×H2
Since the total work done is the same in both scenarios, we can set the equations equal to each other:
10×18×6=15×12×H2
1080=15×12×H2
First, calculate 15×12:
15×12=180
1080=180×H2
H2=1080180=6
Thus, the number of hours per day that 15 men must work to complete the same work in 12 days is 6 hours.
Topper's Solved these Questions
Similar Questions
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View Solution
Knowledge Check
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?A50B60C54D45If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
A6 hoursB(6)1/2 hoursC7 hoursD9 hoursIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?A9B18C16D12
Fifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution