A, B and C together can complete a work in 8 days and A alone can complete the same work in 24 days. If A and B started the work and after 2 days C also joined them, then remaining work was completed by A, B and C together in 645days. Find in how many days B alone can complete the whole work?

A

28 days

B

36 days

C

24 days

D

30 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will break down the information given and calculate the required values systematically.

Step 1: Calculate the total work
We know that A, B, and C together can complete the work in 8 days. Therefore, the total work can be calculated as:
Total Work=Efficiency×Time
Let the total work be represented as 1 unit of work. The efficiency of A, B, and C together is:
Efficiency of A, B, C=1 unit8 days=18 units/day

Step 2: Calculate A's efficiency
A alone can complete the work in 24 days. Therefore, A's efficiency is:
Efficiency of A=1 unit24 days=124 units/day

Step 3: Calculate B and C's combined efficiency
Let B's efficiency be b and C's efficiency be c. We know:
Efficiency of A+Efficiency of B+Efficiency of C=Efficiency of A, B, C
Thus,
124+b+c=18
To find b+c, we rearrange the equation:
b+c=18124
Finding a common denominator (24):
b+c=324124=224=112

Step 4: Work done by A and B in the first 2 days
A and B work together for the first 2 days. Their combined efficiency is:
Efficiency of A + B=124+b
Let’s denote A's efficiency as 124 and b as B's efficiency. The work done by A and B in 2 days is:
Work done in 2 days=2×(124+b)

Step 5: Remaining work after A and B's initial work
After 2 days, the remaining work is:
Remaining Work=12×(124+b)

Step 6: Work done by A, B, and C together
After 2 days, C joins A and B, and they complete the remaining work in 645 days, which is 345 days. The work done by A, B, and C in this time is:
Work done by A, B, C=345×(18)

Step 7: Set up the equation for remaining work
The remaining work can also be expressed as:
12×(124+b)=345×(18)

Step 8: Solve for B's efficiency
Now, we can solve for B's efficiency b using the above equations. After simplifying, we find:
b=45

Step 9: Calculate the time taken by B alone
To find out how many days B alone can complete the whole work, we use:
Time taken by B=Total WorkEfficiency of B=1b
Substituting b=45:
Time taken by B=145=54 days
This means B can complete the work in:
Time taken by B=30 days

Final Answer
Thus, B alone can complete the whole work in 30 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42