A complete the work in 10 days and B in 15 days. In how many days A+B can complete the work?
The correct Answer is:6 days
To solve the problem of how many days A and B can complete the work together, we can follow these steps:
1. Determine the Work Done by A and B Individually:
- A can complete the work in 10 days.
- B can complete the work in 15 days.
2. Calculate the Total Work:
- We can assume the total work to be the least common multiple (LCM) of the days taken by A and B.
- The LCM of 10 and 15 is 30.
- Thus, we can say the total work is 30 units.
3. Calculate the Efficiency of A and B:
- Efficiency is defined as the amount of work done in one day.
- For A:
Efficiency of A=Total WorkDays taken by A=3010=3 units/day
- For B:
Efficiency of B=Total WorkDays taken by B=3015=2 units/day
4. Calculate the Combined Efficiency of A and B:
- Combined efficiency of A and B:
Combined Efficiency=Efficiency of A+Efficiency of B=3+2=5 units/day
5. Calculate the Time Taken by A and B Together:
- Time taken by A and B together to complete the work:
Time=Total WorkCombined Efficiency=305=6 days
Final Answer:
A and B together can complete the work in 6 days.
---
- A can complete the work in 10 days.
- B can complete the work in 15 days.
- We can assume the total work to be the least common multiple (LCM) of the days taken by A and B.
- The LCM of 10 and 15 is 30.
- Thus, we can say the total work is 30 units.
- Efficiency is defined as the amount of work done in one day.
- For A:
Efficiency of A=Total WorkDays taken by A=3010=3 units/day
- For B:
Efficiency of B=Total WorkDays taken by B=3015=2 units/day
- Combined efficiency of A and B:
Combined Efficiency=Efficiency of A+Efficiency of B=3+2=5 units/day
- Time taken by A and B together to complete the work:
Time=Total WorkCombined Efficiency=305=6 days
A and B together can complete the work in 6 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE
10 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
If A & B completed a work together in 6 days . If A completed the same work in 10 days alone . Then in how many days will B complete the same work alone ?
View SolutionA can complete one-third of a work in 5 days and B can complete 40% of the work in 10 days. In how many days both A and B together can complete the work?
View Solution
Knowledge Check
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 daysA can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
A6B4C5D10
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA works thrice as much as B. If A can complete this work in 12 days, then in how many days will both A and B complete this work ?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution