Two persons takes 9 days to complete 2 work. To complete double of that work, in 12 days how many more persons will be required?
2
3
1
4
The correct Answer is:B
Similar Questions
20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
View SolutionIf 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View Solution25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
View SolutionEight person can finish a wotk in 25 days . After 5 days they were requested to complete the work in the next 10 days. How many more persons should join the group to fulfil the requirements?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution