If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?

A

10

B

20

C

30

D

40

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C


Let the required number of men be x.
We have, M 1 D 1 H 1 W 1 = M 2 D 2 H 2 W 2
( 20 ) ( 15 ) ( 10 ) 1 = ( 20 + x ) ( 10 ) ( 12 ) 2
20 + x = 50 x = 30 .

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • 7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?

    A28
    B21
    C14
    D7