12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:270 men


To solve the problem, we will follow these steps:

Step 1: Calculate the total work done by 12 men in 30 days working 9 hours a day.

Total work (in man-hours) = Number of men × Number of days × Number of hours per day

Total work = 12 men × 30 days × 9 hours/day
Total work = 12 × 30 × 9 = 3240 man-hours

Step 2: Determine the total work required for 10 times this work.

Since we need to complete 10 times the original work:

Total work required = 10 × 3240 man-hours
Total work required = 32400 man-hours

Step 3: Calculate the total available work hours with the new conditions.

Now, we need to find out how many men are required to complete this work in 24 days working 5 hours a day.

Total available work hours = Number of men × Number of days × Number of hours per day
Let the number of men required be N.

Total available work hours = N men × 24 days × 5 hours/day
Total available work hours = N×24×5=120N man-hours

Step 4: Set up the equation.

We know that the total available work hours must equal the total work required:

120N = 32400

Step 5: Solve for N.

To find N, divide both sides of the equation by 120:

N = 32400 / 120
N = 270

Conclusion:

The number of men required to complete 10 times the work in 24 days by working 5 hours a day is 270 men.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?

    A30
    B25
    C48
    D35
  • If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

    Aa) 15
    Bb) 12
    Cc) 10
    Dd) 16
  • 18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day

    A32 days
    B45 days
    C36 days
    D40 days