It takes 8,12 and 16 days for X, Y and Z respectively to complete a work. How many days will it take to complete the work if X works on it for 2 days, and then Y works on it for until 25% of the work is left for Z to do, and then Z complete the work?
10 days
12 days
8 days
14 days
The correct Answer is:B
To solve the problem step-by-step, we will break it down into manageable parts.
Step 1: Determine the work done by X, Y, and Z in one day.
- X completes the work in 8 days, so the work done by X in one day is:
Work done by X in 1 day=18
- Y completes the work in 12 days, so the work done by Y in one day is:
Work done by Y in 1 day=112
- Z completes the work in 16 days, so the work done by Z in one day is:
Work done by Z in 1 day=116
Step 2: Calculate the work done by X in 2 days.
- In 2 days, X will complete:
Work done by X in 2 days=2×18=28=14
Step 3: Calculate the remaining work after X works for 2 days.
- The total work is considered as 1 (or 100%). After X completes 14 of the work, the remaining work is:
Remaining work=1−14=34
Step 4: Determine how much work Y needs to do before leaving 25% of the work for Z.
- 25% of the total work is:
25%=25100=14
- Therefore, Y will work until 14 of the work is left, which means Y will complete:
Work done by Y=34−14=24=12
Step 5: Calculate how many days Y takes to complete 12 of the work.
- Since Y does 112 of the work in one day, the number of days Y needs to complete 12 of the work is:
Days taken by Y=12112=12×121=6 days
Step 6: Calculate the work remaining for Z.
- After Y completes 12 of the work, the remaining work for Z is:
Remaining work for Z=14 (as calculated earlier)
Step 7: Calculate how many days Z takes to complete the remaining work.
- Since Z completes 116 of the work in one day, the number of days Z needs to complete 14 of the work is:
Days taken by Z=14116=14×161=4 days
Step 8: Calculate the total time taken to complete the work.
- The total time taken is the sum of the days worked by X, Y, and Z:
Total days=2 (days by X)+6 (days by Y)+4 (days by Z)=12 days
Final Answer:
The total number of days required to complete the work is 12 days.
---
- X completes the work in 8 days, so the work done by X in one day is:
Work done by X in 1 day=18
- Y completes the work in 12 days, so the work done by Y in one day is:
Work done by Y in 1 day=112
- Z completes the work in 16 days, so the work done by Z in one day is:
Work done by Z in 1 day=116
- In 2 days, X will complete:
Work done by X in 2 days=2×18=28=14
- The total work is considered as 1 (or 100%). After X completes 14 of the work, the remaining work is:
Remaining work=1−14=34
- 25% of the total work is:
25%=25100=14
- Therefore, Y will work until 14 of the work is left, which means Y will complete:
Work done by Y=34−14=24=12
- Since Y does 112 of the work in one day, the number of days Y needs to complete 12 of the work is:
Days taken by Y=12112=12×121=6 days
- After Y completes 12 of the work, the remaining work for Z is:
Remaining work for Z=14 (as calculated earlier)
- Since Z completes 116 of the work in one day, the number of days Z needs to complete 14 of the work is:
Days taken by Z=14116=14×161=4 days
- The total time taken is the sum of the days worked by X, Y, and Z:
Total days=2 (days by X)+6 (days by Y)+4 (days by Z)=12 days
The total number of days required to complete the work is 12 days.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (b)
15 Videos
- SURDS BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SURDS EXERCISE - UNIT TEST -1
15 Videos
- TRIANGLES BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLES EXERCISE - Self Assessment Sheet
10 Videos
Similar Questions
Knowledge Check
A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) daysA can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) daysIf A, B and C can respectively complete a piece of work in 20, 24 and 36 days respectively, how many days will they take to complete the work, if they work together?
A81643B614C914D71920
27. 15 people completed a work in 7 days 10 How many days should people take to complete this work?
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionIf A,B and C can respectively complete a piece of work in 20,24 and 36 days respectively .how many days will they take to complete the work, if they work together?
View SolutionA's 2 days' work is equal to B's 3days' work. a complete work in 8 days then to complete the work B will take
View SolutionX can do a piece of work in 40 days. He works it for 8 days and then Y finished it in 16 days How long will they together take to complete the work?
View Solution