A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A

6

B

214

C

812

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's first determine the work rates of A, B, and C.

Step 1: Calculate the work rates of A, B, and C.

1. A's work rate: A can complete the entire work in 8 days.
Work rate of A=18 (work per day)

2. B's work rate: B can complete 35 of the work in 12 days.
To find B's work rate, we first determine how much work B can do in one day:
Work done by B in one day=3/512=360=120
Thus, B's work rate is:
Work rate of B=120 (work per day)

3. C's work rate: C can complete 49 of the work in 8 days.
To find C's work rate, we calculate:
Work done by C in one day=4/98=472=118
Therefore, C's work rate is:
Work rate of C=118 (work per day)

Step 2: Calculate the combined work rate of A and B.

Now, we can add the work rates of A and B to find their combined work rate:
Combined work rate of A and B=18+120

To add these fractions, we need a common denominator. The least common multiple of 8 and 20 is 40.
18=540,120=240
Thus,
Combined work rate of A and B=540+240=740

Step 3: Calculate the work done by A and B in 5 days.

Now we calculate how much work A and B can complete together in 5 days:
Work done by A and B in 5 days=5×740=3540=78

Step 4: Determine the remaining work.

Since A and B completed 78 of the work, the remaining work is:
Remaining work=178=18

Step 5: Calculate the time taken by C to complete the remaining work.

Now we need to find out how long it will take C to complete the remaining 18 of the work. Since C's work rate is 118:
Time taken by C=Remaining workWork rate of C=1/81/18=18×181=188=2.25 days

Final Answer:
C will take 2.25 days to complete the remaining work.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?

    A24 days
    B18 days
    C20 days
    D16 days
  • If A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.

    A3/4 days
    B8/3 days
    C5/2 days
    D3/8 days
  • A completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?

    A3.8 days
    B3.33 days
    C2.22 days
    D4.3 days