A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
6
214
812
9
The correct Answer is:A
To solve the problem step by step, let's first determine the work rates of A, B, and C.
Step 1: Calculate the work rates of A, B, and C.
1. A's work rate: A can complete the entire work in 8 days.
Work rate of A=18 (work per day)
2. B's work rate: B can complete 35 of the work in 12 days.
To find B's work rate, we first determine how much work B can do in one day:
Work done by B in one day=3/512=360=120
Thus, B's work rate is:
Work rate of B=120 (work per day)
3. C's work rate: C can complete 49 of the work in 8 days.
To find C's work rate, we calculate:
Work done by C in one day=4/98=472=118
Therefore, C's work rate is:
Work rate of C=118 (work per day)
Step 2: Calculate the combined work rate of A and B.
Now, we can add the work rates of A and B to find their combined work rate:
Combined work rate of A and B=18+120
To add these fractions, we need a common denominator. The least common multiple of 8 and 20 is 40.
18=540,120=240
Thus,
Combined work rate of A and B=540+240=740
Step 3: Calculate the work done by A and B in 5 days.
Now we calculate how much work A and B can complete together in 5 days:
Work done by A and B in 5 days=5×740=3540=78
Step 4: Determine the remaining work.
Since A and B completed 78 of the work, the remaining work is:
Remaining work=1−78=18
Step 5: Calculate the time taken by C to complete the remaining work.
Now we need to find out how long it will take C to complete the remaining 18 of the work. Since C's work rate is 118:
Time taken by C=Remaining workWork rate of C=1/81/18=18×181=188=2.25 days
Final Answer:
C will take 2.25 days to complete the remaining work.
---
Work rate of A=18 (work per day)
To find B's work rate, we first determine how much work B can do in one day:
Work done by B in one day=3/512=360=120
Thus, B's work rate is:
Work rate of B=120 (work per day)
To find C's work rate, we calculate:
Work done by C in one day=4/98=472=118
Therefore, C's work rate is:
Work rate of C=118 (work per day)
Combined work rate of A and B=18+120
18=540,120=240
Thus,
Combined work rate of A and B=540+240=740
Work done by A and B in 5 days=5×740=3540=78
Remaining work=1−78=18
Time taken by C=Remaining workWork rate of C=1/81/18=18×181=188=2.25 days
C will take 2.25 days to complete the remaining work.
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View Solution
Knowledge Check
A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 daysIf A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.
A3/4 daysB8/3 daysC5/2 daysD3/8 daysA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
A3.8 daysB3.33 daysC2.22 daysD4.3 days
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View Solution