Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?
8 days
12 days
5 days
10 days
The correct Answer is:C
To solve the problem, let's denote the total work as 1 unit. We will also denote the work done by Arjun in one day as A and the work done by Bharath in one day as B.
Step 1: Work done by Arjun in 2 days
Arjun works for 2 days, so the work done by Arjun in 2 days is:
Work done by Arjun=2A
Step 2: Work done by Bharath in 9 days
After Arjun leaves, Bharath completes the remaining work in 9 days. Therefore, the work done by Bharath in 9 days is:
Work done by Bharath=9B
Step 3: Total work equation
Since the total work is 1 unit, we can write the equation:
2A+9B=1(Equation 1)
Step 4: Work done if Arjun worked for 3 days
If Arjun had worked for 3 days, the work done by him would be:
Work done by Arjun in 3 days=3A
Then, Bharath would finish the remaining work in 6 days, so:
Work done by Bharath in 6 days=6B
Step 5: Total work equation for this scenario
The total work in this scenario can also be expressed as:
3A+6B=1(Equation 2)
Step 6: Solve the system of equations
Now we have two equations:
1. 2A+9B=1
2. 3A+6B=1
We can solve these equations simultaneously. Let's multiply Equation 2 by 3 to eliminate B:
9A+18B=3(Equation 3)
Now, we can subtract Equation 1 from Equation 3:
(9A+18B)−(2A+9B)=3−1
7A+9B=2(Equation 4)
Step 7: Substitute to find B
Now we can express B in terms of A using Equation 1:
9B=1−2A⟹B=1−2A9
Substituting B into Equation 4:
7A+9(1−2A9)=2
7A+1−2A=2
5A=1⟹A=15
Step 8: Find B
Now substitute A back to find B:
B=1−2(15)9=1−259=359=115
Step 9: Calculate days for Arjun to complete the task alone
If Arjun can do A=15 of the work in one day, then the number of days Arjun would take to complete the task alone is:
Days for Arjun=1A=115=5 days
Final Answer
Arjun alone can complete the task in 5 days.
Arjun works for 2 days, so the work done by Arjun in 2 days is:
Work done by Arjun=2A
After Arjun leaves, Bharath completes the remaining work in 9 days. Therefore, the work done by Bharath in 9 days is:
Work done by Bharath=9B
Since the total work is 1 unit, we can write the equation:
2A+9B=1(Equation 1)
If Arjun had worked for 3 days, the work done by him would be:
Work done by Arjun in 3 days=3A
Then, Bharath would finish the remaining work in 6 days, so:
Work done by Bharath in 6 days=6B
The total work in this scenario can also be expressed as:
3A+6B=1(Equation 2)
Now we have two equations:
1. 2A+9B=1
2. 3A+6B=1
9A+18B=3(Equation 3)
(9A+18B)−(2A+9B)=3−1
7A+9B=2(Equation 4)
Now we can express B in terms of A using Equation 1:
9B=1−2A⟹B=1−2A9
7A+9(1−2A9)=2
7A+1−2A=2
5A=1⟹A=15
Now substitute A back to find B:
B=1−2(15)9=1−259=359=115
If Arjun can do A=15 of the work in one day, then the number of days Arjun would take to complete the task alone is:
Days for Arjun=1A=115=5 days
Arjun alone can complete the task in 5 days.
Similar Questions
A started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View Solution
Knowledge Check
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 daysA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
A48 daysB88 daysC30 daysD40 days
A and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA alone can complete a task in 3 days and B alone can complete the same task in 6 days. In how manny days can A and B complete it together?
View SolutionA can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
View Solution