Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?

A

8 days

B

12 days

C

5 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, let's denote the total work as 1 unit. We will also denote the work done by Arjun in one day as A and the work done by Bharath in one day as B.

Step 1: Work done by Arjun in 2 days
Arjun works for 2 days, so the work done by Arjun in 2 days is:
Work done by Arjun=2A

Step 2: Work done by Bharath in 9 days
After Arjun leaves, Bharath completes the remaining work in 9 days. Therefore, the work done by Bharath in 9 days is:
Work done by Bharath=9B

Step 3: Total work equation
Since the total work is 1 unit, we can write the equation:
2A+9B=1(Equation 1)

Step 4: Work done if Arjun worked for 3 days
If Arjun had worked for 3 days, the work done by him would be:
Work done by Arjun in 3 days=3A
Then, Bharath would finish the remaining work in 6 days, so:
Work done by Bharath in 6 days=6B

Step 5: Total work equation for this scenario
The total work in this scenario can also be expressed as:
3A+6B=1(Equation 2)

Step 6: Solve the system of equations
Now we have two equations:
1. 2A+9B=1
2. 3A+6B=1

We can solve these equations simultaneously. Let's multiply Equation 2 by 3 to eliminate B:
9A+18B=3(Equation 3)

Now, we can subtract Equation 1 from Equation 3:
(9A+18B)(2A+9B)=31
7A+9B=2(Equation 4)

Step 7: Substitute to find B
Now we can express B in terms of A using Equation 1:
9B=12AB=12A9

Substituting B into Equation 4:
7A+9(12A9)=2
7A+12A=2
5A=1A=15

Step 8: Find B
Now substitute A back to find B:
B=12(15)9=1259=359=115

Step 9: Calculate days for Arjun to complete the task alone
If Arjun can do A=15 of the work in one day, then the number of days Arjun would take to complete the task alone is:
Days for Arjun=1A=115=5 days

Final Answer
Arjun alone can complete the task in 5 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?

    A48 days
    B88 days
    C30 days
    D40 days