A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
11
12
13
14
The correct Answer is:A
Ae=124=4.16%
Be=130=3.33%
Ce=140=2.5%
माना कि कार्य x दिन में पूरा हुआ।
∴x×4.16+x×3.33+(x−4)×2.5=100
⇒ 7.5x + 2.5x-10 = 100
⇒10x=110
⇒x=11
अर्थात् कार्य 11 दिन में पूरा हुआ।
Similar Questions
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
View SolutionX, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View Solution