X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A

660/47

B

640/47

C

680/47

D

665/47

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how many days it took for X, Y, and Z to complete the work together, given that Y left 4 days before the work was completed.

1. Determine the Work Rates of X, Y, and Z:
- X can complete the work in 30 days, so X's work rate is 130 of the work per day.
- Y can complete the work in 40 days, so Y's work rate is 140 of the work per day.
- Z can complete the work in 50 days, so Z's work rate is 150 of the work per day.

2. Calculate the Combined Work Rate:
- The combined work rate of X, Y, and Z when they work together is:
Combined Rate=130+140+150
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 30, 40, and 50 is 600.
- Convert each fraction:
130=20600,140=15600,150=12600
- Now add them:
Combined Rate=20+15+12600=47600

3. Determine the Total Work Done:
- Let the total work be represented as 600 units (as we assumed).
- Since Y leaves 4 days before the work is completed, let D be the total number of days taken to complete the work.
- This means Y worked for D4 days.

4. Calculate Work Done by Each Worker:
- Work done by X in D days: D30
- Work done by Y in D4 days: D440
- Work done by Z in D days: D50

5. Set Up the Equation:
- The total work done by all three workers must equal 600 units:
D30+D440+D50=1
- To eliminate the fractions, multiply through by 600 (the common denominator):
20D+15(D4)+12D=600

6. Simplify the Equation:
- Distributing the terms:
20D+15D60+12D=600
- Combine like terms:
47D60=600
- Add 60 to both sides:
47D=660
- Divide by 47:
D=6604714.04 days

7. Conclusion:
- Since the number of days must be a whole number, we round up to the nearest whole number, which is 15 days.

Final Answer:
The work was completed in 15 days.

|


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9
  • A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A13
    B12
    C14
    D11
  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10