X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
660/47
640/47
680/47
665/47
The correct Answer is:A
To solve the problem, we need to determine how many days it took for X, Y, and Z to complete the work together, given that Y left 4 days before the work was completed.
1. Determine the Work Rates of X, Y, and Z:
- X can complete the work in 30 days, so X's work rate is 130 of the work per day.
- Y can complete the work in 40 days, so Y's work rate is 140 of the work per day.
- Z can complete the work in 50 days, so Z's work rate is 150 of the work per day.
2. Calculate the Combined Work Rate:
- The combined work rate of X, Y, and Z when they work together is:
Combined Rate=130+140+150
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 30, 40, and 50 is 600.
- Convert each fraction:
130=20600,140=15600,150=12600
- Now add them:
Combined Rate=20+15+12600=47600
3. Determine the Total Work Done:
- Let the total work be represented as 600 units (as we assumed).
- Since Y leaves 4 days before the work is completed, let D be the total number of days taken to complete the work.
- This means Y worked for D−4 days.
4. Calculate Work Done by Each Worker:
- Work done by X in D days: D30
- Work done by Y in D−4 days: D−440
- Work done by Z in D days: D50
5. Set Up the Equation:
- The total work done by all three workers must equal 600 units:
D30+D−440+D50=1
- To eliminate the fractions, multiply through by 600 (the common denominator):
20D+15(D−4)+12D=600
6. Simplify the Equation:
- Distributing the terms:
20D+15D−60+12D=600
- Combine like terms:
47D−60=600
- Add 60 to both sides:
47D=660
- Divide by 47:
D=66047≈14.04 days
7. Conclusion:
- Since the number of days must be a whole number, we round up to the nearest whole number, which is 15 days.
Final Answer:
The work was completed in 15 days.
- X can complete the work in 30 days, so X's work rate is 130 of the work per day.
- Y can complete the work in 40 days, so Y's work rate is 140 of the work per day.
- Z can complete the work in 50 days, so Z's work rate is 150 of the work per day.
- The combined work rate of X, Y, and Z when they work together is:
Combined Rate=130+140+150
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 30, 40, and 50 is 600.
- Convert each fraction:
130=20600,140=15600,150=12600
- Now add them:
Combined Rate=20+15+12600=47600
- Let the total work be represented as 600 units (as we assumed).
- Since Y leaves 4 days before the work is completed, let D be the total number of days taken to complete the work.
- This means Y worked for D−4 days.
- Work done by X in D days: D30
- Work done by Y in D−4 days: D−440
- Work done by Z in D days: D50
- The total work done by all three workers must equal 600 units:
D30+D−440+D50=1
- To eliminate the fractions, multiply through by 600 (the common denominator):
20D+15(D−4)+12D=600
- Distributing the terms:
20D+15D−60+12D=600
- Combine like terms:
47D−60=600
- Add 60 to both sides:
47D=660
- Divide by 47:
D=66047≈14.04 days
- Since the number of days must be a whole number, we round up to the nearest whole number, which is 15 days.
The work was completed in 15 days.
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution
Knowledge Check
A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution