Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?
10
6
4
2
The correct Answer is:C
To solve the problem, we will break it down into manageable steps:
Step 1: Define Variables
Let the number of days taken by A, B, and C together to complete the work be D.
Step 2: Establish Relationships
From the problem, we know:
1. B and C together take 50% more days than A, B, and C together.
- This means:
Days taken by B and C=D+0.5D=1.5D
2. A and B together take 83 more days than A, B, and C together.
- This means:
Days taken by A and B=D+83
Step 3: Calculate Work Efficiency
Let’s denote the work done by A, B, and C in one day as a,b,c respectively. The total work done in one day by A, B, and C together is:
a+b+c=1D
The work done by B and C together in one day is:
b+c=11.5D=23D
The work done by A and B together in one day is:
a+b=1D+83=13D+83=33D+8
Step 4: Set Up Equations
From the relationships established, we can set up equations:
1. From a+b+c=1D and b+c=23D:
a=1D−23D=3−23D=13D
2. From a+b=33D+8:
13D+b=33D+8
Rearranging gives:
b=33D+8−13D
Step 5: Solve for D
Now we can substitute b back into the equations and solve for D. However, we also know that B received ₹120 out of ₹450, which gives us the ratio of their efficiencies:
ba+b+c=120450=415
This implies:
b=415(a+b+c)=415⋅1=415
Step 6: Calculate Total Work
Using the ratios of efficiencies:
- If a=5k, b=4k, and c=6k (from the earnings ratio), then:
5k+4k+6k=15k
Thus, the total work can be expressed as:
D=15(5+4+6)=1515=1
Step 7: Find Days Taken
Since we have established that D is the total number of days taken by A, B, and C together, we can conclude that:
D=15 days
Final Answer
Thus, A, B, and C together completed the whole work in 15 days.
Let the number of days taken by A, B, and C together to complete the work be D.
From the problem, we know:
1. B and C together take 50% more days than A, B, and C together.
- This means:
Days taken by B and C=D+0.5D=1.5D
2. A and B together take 83 more days than A, B, and C together.
- This means:
Days taken by A and B=D+83
Let’s denote the work done by A, B, and C in one day as a,b,c respectively. The total work done in one day by A, B, and C together is:
a+b+c=1D
The work done by B and C together in one day is:
b+c=11.5D=23D
The work done by A and B together in one day is:
a+b=1D+83=13D+83=33D+8
From the relationships established, we can set up equations:
1. From a+b+c=1D and b+c=23D:
a=1D−23D=3−23D=13D
2. From a+b=33D+8:
13D+b=33D+8
Rearranging gives:
b=33D+8−13D
Now we can substitute b back into the equations and solve for D. However, we also know that B received ₹120 out of ₹450, which gives us the ratio of their efficiencies:
ba+b+c=120450=415
This implies:
b=415(a+b+c)=415⋅1=415
Using the ratios of efficiencies:
- If a=5k, b=4k, and c=6k (from the earnings ratio), then:
5k+4k+6k=15k
Thus, the total work can be expressed as:
D=15(5+4+6)=1515=1
Since we have established that D is the total number of days taken by A, B, and C together, we can conclude that:
D=15 days
Thus, A, B, and C together completed the whole work in 15 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?
A10B6C4D2A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
A9 daysB12 daysC18 daysD24 daysA and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?
A8B16C12D15
A piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View SolutionA and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View Solution