16 days after the 20% typist left the job it was decided to complete the work on time by increasing the work-force again. By how much percentage increase in work-force is requried?
100%
50%
200%
none of these
The correct Answer is:D
Step by step video, text & image solution for 16 days after the 20% typist left the job it was decided to complete the work on time by increasing the work-force again. By how much percentage increase in work-force is requried? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
If the radius of a circle is increased by 20% then by how much will its area be increased?
View SolutionMr. Stenley employed a tain number of typists for his project. 8 days later 20% of the typist left the job and it was found that it took as much time complete the rest work from then as the entire work needed to all the employed typists. The average speed of a typist is 20 pages/hour.
Minimum how many typist could be employed?
View Solution
Knowledge Check
Mr. Stenley employed a tain number of typists for his project. 8 days later 20% of the typist left the job and it was found that it took as much time complete the rest work from then as the entire work needed to all the employed typists. The average speed of a typist is 20 pages/hour.
Minimum how many typist could be employed?A100%B50%C200%Dnone of these30 men can do a piece of work in 14 days. After how many days 10 men left the work that work should be done in 16 days?
A10B5C16Dcan’t be determinedMr. Stenley employed a tain number of typists for his project. 8 days later 20% of the typist left the job and it was found that it took as much time complete the rest work from then as the entire work needed to all the employed typists. The average speed of a typist is 20 pages/hour.
Minimum how many typist could be employed?A15B18C68D78
Mr. stenley employed a certain number of typist for his project. 8 days later 20% of the typist left the job and it was found that it took as much time to complete the rest work from then as the entire work needed with all the employed typists. The average speed of a typist is 20 pages/hour. Minimum how many typist could be employed?
View SolutionMr. stenley employed a certain number of typist for his project. 8 days later 20% of the typist left the job and it was found that it took as much time to complete the rest work from then as the entire work needed with all the employed typists. The average speed of a typist is 20 pages/hour. Minimum how many typist could be employed?
View SolutionA contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
View Solution3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?
View SolutionA man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?
View Solution