Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

A

12

B

8

C

6

D

3

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to break it down step by step.

Step 1: Understand the total work done
Let’s denote the total work required to reap the field as 1 unit of work.

Step 2: Calculate the combined work rate of both persons
Since both persons can reap the field together in 2 days, their combined work rate is:
Combined work rate=1 unit2 days=12 units per day

Step 3: Determine the work done by the first person
According to the problem, the first person reaped one-third of the field:
Work done by the first person=13 units

Step 4: Calculate the time taken by the first person to reap his share
Let’s denote the time taken by the first person to reap his share as t1. Since he works alone, we can express his work rate as r1:
r1=13 units in t1 days

Step 5: Determine the work done by the second person
The remaining work done by the second person is:
Work done by the second person=113=23 units

Step 6: Calculate the time taken by the second person
Let’s denote the time taken by the second person to reap his share as t2. Since they worked alternatively for a total of 4 days, we can express this as:
t1+t2=4 days

Step 7: Work rates of the two persons
Let’s denote the work rates of the first and second persons as r1 and r2 respectively. From the combined work rate:
r1+r2=12 units per day

Step 8: Express the work done by the second person
Since the second person worked for t2 days, we can express the work done by him as:
r2t2=23 units

Step 9: Substitute t2 in terms of t1
From the equation t1+t2=4, we can express t2 as:
t2=4t1

Step 10: Substitute into the work equation
Substituting t2 into the work done by the second person:
r2(4t1)=23

Step 11: Solve for t1 and t2
Now we have two equations:
1. r1+r2=12
2. r2(4t1)=23

Using the first equation, we can express r2 in terms of r1:
r2=12r1

Substituting this into the second equation gives us:
(12r1)(4t1)=23

Step 12: Solve the equations to find individual work rates
This will lead us to find the values of r1 and r2. Once we have r2, we can find out how long it takes for the faster person to reap the whole field alone.

Step 13: Calculate the time for the faster person
Let’s assume the faster person is the second person (as he worked more). The time taken by the second person to reap the whole field alone is:
Time=1 unitr2

Final Step: Conclusion
After solving the equations, we can find the exact time taken by the faster person to reap the whole field alone.

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone ?

    A72 days
    B73 days
    C49 days
    D62 days
  • 42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B6
    C14
    D16
  • 56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B8
    C14
    D16