Anne, Benne and Cenne are three friends. Anne and Benne are twins. Benne takes 2 days more than Cenne to complete the work. If Anne starts a work and 3 days later Benne joins him, then .the work gets completed in 3 more days. Working together Anne, Benne and Cenne can complete thrice the original work in 6 days. In how many days Benne can complete twice the original work with double the efficiency working alone?
2
3
4
6
The correct Answer is:D
To solve the problem step by step, let's denote the time taken by Cenne to complete the work as C days. Therefore, Benne takes C+2 days to complete the same work.
1. Understanding the Work Rates:
- The work rate of Cenne is 1C (work done per day).
- The work rate of Benne is 1C+2.
- The work rate of Anne (who is a twin of Benne) is also 1C+2.
2. Setting Up the First Equation:
- Anne works alone for 3 days, completing 3C+2 of the work.
- Then Benne joins Anne, and they work together for 3 more days. The total work done in these 3 days is 3(1C+2+1C+2)=3×2C+2=6C+2.
- The total work done is 3C+2+6C+2=9C+2.
- This total work equals 1 (the whole work), so we have:
9C+2=1
- From this, we can solve for C:
9=C+2⟹C=7
3. Finding Benne's Time to Complete the Work:
- Since C=7, Benne's time to complete the work is:
C+2=7+2=9 days
4. Working Together:
- Now we know the rates:
- Anne's rate: 19
- Benne's rate: 19
- Cenne's rate: 17
- Together, they can complete:
19+19+17=29+17
- To combine these fractions, find a common denominator (63):
2×763+1×963=14+963=2363
- Thus, they can complete 2363 of the work in one day.
5. Calculating Time for Thrice the Work:
- To complete thrice the original work, they will take:
Time=32363=3×6323=18923≈8.22 days
6. Benne's Efficiency:
- If Benne works alone at double efficiency, his rate becomes 2×19=29.
- To complete twice the original work:
Time=229=2×9=18 days
Final Answer:
Benne can complete twice the original work with double the efficiency in 18 days.
- The work rate of Cenne is 1C (work done per day).
- The work rate of Benne is 1C+2.
- The work rate of Anne (who is a twin of Benne) is also 1C+2.
- Anne works alone for 3 days, completing 3C+2 of the work.
- Then Benne joins Anne, and they work together for 3 more days. The total work done in these 3 days is 3(1C+2+1C+2)=3×2C+2=6C+2.
- The total work done is 3C+2+6C+2=9C+2.
- This total work equals 1 (the whole work), so we have:
9C+2=1
- From this, we can solve for C:
9=C+2⟹C=7
- Since C=7, Benne's time to complete the work is:
C+2=7+2=9 days
- Now we know the rates:
- Anne's rate: 19
- Benne's rate: 19
- Cenne's rate: 17
- Together, they can complete:
19+19+17=29+17
- To combine these fractions, find a common denominator (63):
2×763+1×963=14+963=2363
- Thus, they can complete 2363 of the work in one day.
- To complete thrice the original work, they will take:
Time=32363=3×6323=18923≈8.22 days
- If Benne works alone at double efficiency, his rate becomes 2×19=29.
- To complete twice the original work:
Time=229=2×9=18 days
Benne can complete twice the original work with double the efficiency in 18 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
Anne, Benne and Cenne are three friends. Anne and Benne are twins. Benne takes 2 days more than Cenne to complete the work. If Anne starts a work and 3 days later Benne joins him, then .the work gets completed in 3 more days. Working together Anne, Benne and Cenne can complete thrice the original work in 6 days. In how many days Benne can complete twice the original work with double the efficiency working alone?
A2B3C4D6A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA can complete a work in 10 days and B can complete it in 15 days. If A starts the work and 5 days later B also joins him, then in how many days the work will be finished?
View SolutionA can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
View SolutionSunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?
View Solution