Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
₹ 900
₹ 1200
₹ 1000
none of these
The correct Answer is:C
Step by step video, text & image solution for Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Topper's Solved these Questions
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?
ARs. 900BRs. 1200CRs. 1000Dnone of theseA man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
A5B5511C1/11D11S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left
A3/5B1/3C1/2D2/5
If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?
View SolutionA can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View Solution