A can build up a wall in 8 days while B can break it in 3 days,
A has worked for 4 days and then B joined to work with A for
another 2 days only. In how many days will A alone build up
the remaining part of wall?
1313 days
713 days
613 days
7 days
The correct Answer is:(b)
To solve the problem step by step, let's break it down:
Step 1: Determine the work done by A in 4 days
A can build a wall in 8 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=18
In 4 days, the work done by A is:
Work done by A in 4 days=4×18=48=12
Hint: Remember that work done is a fraction of the total work based on the number of days worked.
Step 2: Determine the work done by B in one day
B can break the wall in 3 days. Therefore, the work done by B in one day is:
Work done by B in 1 day=−13
(The negative sign indicates that B is breaking down the wall.)
Step 3: Calculate the combined work done by A and B in one day
The combined work done by A and B in one day is:
Work done by A and B in 1 day=18−13
To perform this subtraction, we need a common denominator, which is 24:
18=324,13=824
Thus,
Work done by A and B in 1 day=324−824=−524
Step 4: Calculate the work done by A and B together in 2 days
Now, we calculate the work done by A and B together in 2 days:
Work done by A and B in 2 days=2×(−524)=−1024=−512
Step 5: Calculate the total work done after 6 days
After A works alone for 4 days and then A and B work together for 2 days, the total work done is:
Total work done=12−512
To perform this subtraction, we convert 12 to have a common denominator of 12:
12=612
Thus,
Total work done=612−512=112
Step 6: Determine the remaining work
The total work of the wall is considered as 1 (the whole wall). Therefore, the remaining work is:
Remaining work=1−112=1112
Step 7: Calculate the time A will take to complete the remaining work
A can complete 18 of the wall in one day. To find out how many days A will take to complete 1112 of the wall:
Days required by A=Remaining workWork done by A in 1 day=111218=1112×8=8812=223
This means A will take 223 days, which is approximately 7 days and 1 hour.
Final Answer
A will take 223 days to build the remaining part of the wall.
---
A can build a wall in 8 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=18
In 4 days, the work done by A is:
Work done by A in 4 days=4×18=48=12
Hint: Remember that work done is a fraction of the total work based on the number of days worked.
B can break the wall in 3 days. Therefore, the work done by B in one day is:
Work done by B in 1 day=−13
(The negative sign indicates that B is breaking down the wall.)
The combined work done by A and B in one day is:
Work done by A and B in 1 day=18−13
To perform this subtraction, we need a common denominator, which is 24:
18=324,13=824
Thus,
Work done by A and B in 1 day=324−824=−524
Now, we calculate the work done by A and B together in 2 days:
Work done by A and B in 2 days=2×(−524)=−1024=−512
After A works alone for 4 days and then A and B work together for 2 days, the total work done is:
Total work done=12−512
To perform this subtraction, we convert 12 to have a common denominator of 12:
12=612
Thus,
Total work done=612−512=112
The total work of the wall is considered as 1 (the whole wall). Therefore, the remaining work is:
Remaining work=1−112=1112
A can complete 18 of the wall in one day. To find out how many days A will take to complete 1112 of the wall:
Days required by A=Remaining workWork done by A in 1 day=111218=1112×8=8812=223
This means A will take 223 days, which is approximately 7 days and 1 hour.
A will take 223 days to build the remaining part of the wall.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View Solution
Knowledge Check
A can build up a structure in 8 days and B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only . In how many days will A alone builed up the remaining part of the structure ?
A10 daysB9 daysC713 daysD13 daysA can do a work in 12 days when he had worked for 3 days B joined him if they complete the work in 3 more days in how many days can B alone finish the work?
A6 daysB12 daysC4 daysD8 daysA can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
A12B68C72D90
A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA and B can do a work in 8 days. B alone can do it in 24 days. In how many days, A alone can do the same work?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
View Solution