Two workers A and B working together completed a job in 5
days. If A worked twice as efficiently as he actually did and
B worked 1/3 as efficiently as he actually did, the work would
have completed in 3 days. Fine the time for A to complete
the job alone.

A

614 days

B

534 days

C

5 days

D

3 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(a)


To solve the problem step by step, let's denote the time taken by worker A to complete the job alone as A days and the time taken by worker B to complete the job alone as B days.

Step 1: Set up the equations based on the given information.
From the problem, we know that A and B together complete the job in 5 days. Therefore, their combined work rate can be expressed as:
1A+1B=15

Step 2: Analyze the second condition.
If A worked twice as efficiently, he would complete the job in A2 days. If B worked one-third as efficiently, he would take 3B days to complete the job. Thus, their combined work rate under these new conditions can be expressed as:
2A+13B=13

Step 3: Rewrite the equations.
Now we have two equations:
1. 1A+1B=15 (Equation 1)
2. 2A+13B=13 (Equation 2)

Step 4: Solve Equation 1 for 1B.
From Equation 1, we can express 1B in terms of 1A:
1B=151A

Step 5: Substitute 1B into Equation 2.
Substituting 1B into Equation 2 gives:
2A+13(151A)=13

Step 6: Simplify the equation.
To simplify the second term:
13(151A)=135AA5
Thus, our equation becomes:
2A+5A3(A5)=13

Step 7: Clear the fractions by multiplying through by 3A(A5).
Multiplying through by 3A(A5) gives:
6(A5)+5A2=A(A5)

Step 8: Rearranging the equation.
Expanding and rearranging gives:
6A30+5A2=A25A
4A2+11A30=0

Step 9: Solve the quadratic equation.
Using the quadratic formula A=b±b24ac2a:
A=11±11244(30)24
A=11±121+4808
A=11±6018

Step 10: Calculate the positive root.
Since time cannot be negative, we take the positive root:
A=11+6018

Final Answer:
Thus, the time taken by worker A to complete the job alone is approximately 25/4 days or 6.25 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Two workers A and B working together completed a job in 5
    days. If A worked twice as efficiently as he actually did and
    B worked 1/3 as efficiently as he actually did, the work would
    have completed in 3 days. Fine the time for A to complete
    the job alone.

    A612
    B614
    C634
    D1212
  • Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 13 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require

    A515 days
    B614 days
    C712 days
    D834 days
  • Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :

    A8 days
    B3835 days
    C152
    D1313