A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three working together can complete the job in 24 days then the number of days. A alone will take to finish the job is: a 100 b 96 c 95 d 90
Correct option b 96Explanation: Correct option Explanation: Since we know efficiency of a person’s will know efficiency of a person’s will remain same. So we will balance it.A’s efficiency : 5 unitsB’s efficiency : 4 unitsTotal efficiency : 20 unitsSo C’s efficiency 20 – 5 – 4 = 11 unitsTotal work = 24days × 20units/day⇒480 units.A alone will do whole work in 480/5 = 96 days
Related Solutions
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is
View SolutionA takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionB और C मिलकर एक काम को करने में जितना समय लेते हैं, उससे तीन गुणा अधिक समयA लेता है। A और C मिलकर उसी काम को करने में जितना समय लेते हैं, B उससे चार गुणा अधिक समय लेता है। यदि तीनों मिलकर उस काम को 24 दिन में पूरा कर सकते हैं, तो A के अकेले उस काम को करने में कितने दिन लगेंगे?
View SolutionB takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View SolutionIf A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
View SolutionIf A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?
View SolutionTo complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionA and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
View SolutionB is twice as fast as A and C is three times as fast as A. If B alone can complete a job in 12 days, how long will A, B and C take to complete the same job together?
View SolutionTo complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View SolutionTo do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is
View Solutionএকটি কাজ A ও B একা একা যথাক্রমে 10 দিনে ও 15 দিনে করতে পারে। প্রথমে A একা 4 দিনে ও পরে B একা 5 দিনে কাজ করে চলে যায়। বাকি কাজটি C এসে 4 দিনে শেষ করে। তারা তিনজন একত্রে কাজটি কতদিনে শেষ করতে পারবে ?
View SolutionA alone takes 6 days less than the number of days taken by B alone to finish a job. If both A and B together can finish the job in 4 days . Find the time taken by B alone to finish the job.
View SolutionA and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone? (A) 30 days (B) 25 days (C) 24 days (D) 15 days
View SolutionA और B दिए गए किसी काम को 8 दिन में कार सकता है ,बी और C उसी काम को 12 दिनों में कर सकते है और A,B ,C उसे 6 दिन में पूरा में पूरा कर सकते है A और c द्वारा उस काम को पूरा करने में कितने दिन लगेंगे ?
View Solution