If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?
36
6
18
12
The correct Answer is:C
To solve the problem step by step, let's denote the work done by A, B, and C in terms of their efficiencies.
Step 1: Determine the work done by A, B, and C together
Let the total work be represented as 1 unit of work. If A, B, and C together can complete the job in 4 days, their combined efficiency is:
Efficiency of A, B, and C=1 unit of work4 days=14 units/day
Step 2: Determine the work done by A and C together
If A and C together can complete the job in 4.5 days, their combined efficiency is:
Efficiency of A and C=1 unit of work4.5 days=14.5 units/day=29 units/day
Step 3: Determine the work done by B and C together
If B and C together can complete the job in 12 days, their combined efficiency is:
Efficiency of B and C=1 unit of work12 days=112 units/day
Step 4: Set up equations for individual efficiencies
Let the efficiencies of A, B, and C be represented as a, b, and c respectively. We can set up the following equations based on the efficiencies calculated:
1. a+b+c=14 (from A, B, and C)
2. a+c=29 (from A and C)
3. b+c=112 (from B and C)
Step 5: Solve the equations
From equation (2), we can express a in terms of c:
a=29−c
From equation (3), we can express b in terms of c:
b=112−c
Now substitute a and b into equation (1):
(29−c)+(112−c)+c=14
Combine like terms:
29+112−c=14
Step 6: Find a common denominator and simplify
The common denominator of 9, 12, and 4 is 36. Rewrite each fraction:
29=836,112=336,14=936
Now substitute:
836+336−c=936
1136−c=936
c=1136−936=236=118
Step 7: Calculate the time taken by C alone
Since c=118, this means C can complete the job alone in:
Time taken by C=1 unit of workc=1118=18 days
Thus, C alone can do the job in 18 days.
Let the total work be represented as 1 unit of work. If A, B, and C together can complete the job in 4 days, their combined efficiency is:
Efficiency of A, B, and C=1 unit of work4 days=14 units/day
If A and C together can complete the job in 4.5 days, their combined efficiency is:
Efficiency of A and C=1 unit of work4.5 days=14.5 units/day=29 units/day
If B and C together can complete the job in 12 days, their combined efficiency is:
Efficiency of B and C=1 unit of work12 days=112 units/day
Let the efficiencies of A, B, and C be represented as a, b, and c respectively. We can set up the following equations based on the efficiencies calculated:
1. a+b+c=14 (from A, B, and C)
2. a+c=29 (from A and C)
3. b+c=112 (from B and C)
From equation (2), we can express a in terms of c:
a=29−c
b=112−c
(29−c)+(112−c)+c=14
29+112−c=14
The common denominator of 9, 12, and 4 is 36. Rewrite each fraction:
29=836,112=336,14=936
836+336−c=936
1136−c=936
c=1136−936=236=118
Since c=118, this means C can complete the job alone in:
Time taken by C=1 unit of workc=1118=18 days
Topper's Solved these Questions
Similar Questions
A can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionA can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?
View Solution
Knowledge Check
A and B can do a work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?
A12 daysB20 daysC24 daysD28 daysA,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
A12B16C20D24A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
A6B12C9D15
A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View SolutionWorking together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View Solution