Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was: a 24 b 20 c 16 d 18
Correct option b 20 Explanation: Let there were N carpenters in the beginning According to question
Related Solutions
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
View SolutionSome carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?
View SolutionSome staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?
View SolutionA certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :
View SolutionA certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :
View SolutionSome mans promised to do a work in 10 days but 8 of them were absent and remaining did the work in 18 days. What was the original number of mans?
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View Solutionmen can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View SolutionA and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone? (A) 30 days (B) 25 days (C) 24 days (D) 15 days
View SolutionIf A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days then in how many days can C alone do the job?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?
View SolutionA can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in
View Solution30 men can complete a job in 40 days. However, after 24 days some men out of the assigned 30 left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is
View SolutionIf 12 carpenters working 6 hours a day can make 460 chairs in 24 days, then how many chairs can 18 carpenters make in 36 days working 8 hours a day?
View Solution15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days
View SolutionIf 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?
View Solution