A does half as much work as B in one third of the time taken by B. If together they take 10 days to complete a work then the time taken by B along to do it would have been : a 30 days b 25 days c 6 days d 12 days
Correct option b 25 daysExplanation:A : BTime 1 : 3 Description same as Q no 135 Work 1 : 2Now equal the work of A and BDescription same as Q.no. 135Total work = 10 days × 5 = 50 unitsB alone completes whole work in = 50/2 = 25 days
Related Solutions
The time taken by B to do a piece of work is (1)/(6) A does half of the work in the time. If both of them take a total of 10 days to do the work, then in how many days will B alone complete the work?
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionA and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View SolutionA can do 50% of the work done by B in one-third of the time taken by B. If both of them work together, the work will be completed in 10 days. Accordingly, in how many days will B do the same work alone?
View SolutionA, B and C can complete a work in 24 days, 9 days and 12 days respectively. B and C start the work but they have to leave it after 3 days. The time taken by A to do the remaining work is
View Solutionकिसी कार्य को A, B तथा c क्रमशः 24 दिन, 9 दिन व 12 दिन में पूरा कर सकते है। B तथा C कार्य प्रारम्भ करते है , परन्तु उन्हें 3 दिन बाद यह कार्य छोड़ना पड़ता है। शेष कार्य को करने में A को लगा समय है
View SolutionA and B working together can complete the work in 12 days. A can complete the work in 20 days. If B does work for half day each day, then in what time can the work be completed.
View SolutionA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionThe time taken by B to do a piece of work is (1)/(6) In time, A does half the work. If both together can finish the work in 10 days, then in how many days will B do it?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View SolutionA can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C to do the work together.
View SolutionIf A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A + B + C + D ?
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View SolutionA and B together can do a piece of work in 12 days. A alone can complete it in 20 days. If B works only for half a day every day, then in how many days will A and B together complete the work?
View Solution