In the given questions, two quantities are given, one as Quantity I and another as Quantity II. You have to determine relationship between two quantities and choose the appropriate option.
A and B can together finish a piece of work in 20 days. If B starts working and after 15 days is replaced by A, A can finish the remaining work in 24 days.
Quantity I. Number of days taken by B alone to finish the same pices of work.
Quantity II. Number of days taken by A alone to finish the same piece of work.

A

If Quantity I Quantity II

B

If Quantity I>Quantity II

C

If Quantity I<Quantity II

D

If Quantity I=Quantity II or the relationship cannot be established from the information that is given

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine the number of days taken by A and B to complete the work individually based on the information provided.

1. Understanding the Work Rate:
- Let the number of days A takes to complete the work alone be X.
- Let the number of days B takes to complete the work alone be Y.
- The work done by A in one day is 1X.
- The work done by B in one day is 1Y.
- Together, A and B can complete the work in 20 days, so:
1X+1Y=120

2. Work Done by B in 15 Days:
- B works for 15 days, so the work done by B in those 15 days is:
Work by B=15×1Y=15Y

3. Work Done by A in 24 Days:
- After B works for 15 days, A works for 24 days to finish the remaining work. The work done by A in those 24 days is:
Work by A=24×1X=24X

4. Total Work Equation:
- The total work done by both A and B must equal 1 (the whole work):
15Y+24X=1

5. Setting Up the Equations:
- We now have two equations:
1. 1X+1Y=120 (Equation 1)
2. 15Y+24X=1 (Equation 2)

6. Expressing Y in terms of X:
- From Equation 1, we can express 1Y:
1Y=1201X
- Thus,
Y=20XX20

7. Substituting Y in Equation 2:
- Substitute Y in Equation 2:
15(X20)20X+24X=1
- Simplifying this gives:
15(X20)+48020X=1
- Multiply through by 20X:
15(X20)+480=20X
- Expanding and rearranging gives:
15X300+480=20X180=5XX=36

8. Finding Y:
- Substitute X=36 back into the equation for Y:
1Y=120136
- Finding a common denominator (LCM of 20 and 36 is 180):
1Y=95180=4180Y=45

Conclusion:
- Quantity I (Days taken by B alone) = 45 days
- Quantity II (Days taken by A alone) = 36 days

Comparison:
- Quantity I (45 days) > Quantity II (36 days)

Final Answer:
- Quantity I is greater than Quantity II.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

    A3 days
    B5 days
    C7 days
    D11 days
  • A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

    A5 days
    B7 days
    C11 days
    D3 days
  • If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in

    A427 days
    B30 days
    C847 days
    D760 days