In the given questions, two quantities are given, one as Quantity I and another as Quantity II. You have to determine relationship between two quantities and choose the appropriate option.
A and B can together finish a piece of work in 20 days. If B starts working and after 15 days is replaced by A, A can finish the remaining work in 24 days.
Quantity I. Number of days taken by B alone to finish the same pices of work.
Quantity II. Number of days taken by A alone to finish the same piece of work.
If Quantity I≥ Quantity II
If Quantity I>Quantity II
If Quantity I<Quantity II
If Quantity I=Quantity II or the relationship cannot be established from the information that is given
The correct Answer is:B
To solve the problem, we need to determine the number of days taken by A and B to complete the work individually based on the information provided.
1. Understanding the Work Rate:
- Let the number of days A takes to complete the work alone be X.
- Let the number of days B takes to complete the work alone be Y.
- The work done by A in one day is 1X.
- The work done by B in one day is 1Y.
- Together, A and B can complete the work in 20 days, so:
1X+1Y=120
2. Work Done by B in 15 Days:
- B works for 15 days, so the work done by B in those 15 days is:
Work by B=15×1Y=15Y
3. Work Done by A in 24 Days:
- After B works for 15 days, A works for 24 days to finish the remaining work. The work done by A in those 24 days is:
Work by A=24×1X=24X
4. Total Work Equation:
- The total work done by both A and B must equal 1 (the whole work):
15Y+24X=1
5. Setting Up the Equations:
- We now have two equations:
1. 1X+1Y=120 (Equation 1)
2. 15Y+24X=1 (Equation 2)
6. Expressing Y in terms of X:
- From Equation 1, we can express 1Y:
1Y=120−1X
- Thus,
Y=20XX−20
7. Substituting Y in Equation 2:
- Substitute Y in Equation 2:
15(X−20)20X+24X=1
- Simplifying this gives:
15(X−20)+48020X=1
- Multiply through by 20X:
15(X−20)+480=20X
- Expanding and rearranging gives:
15X−300+480=20X⟹180=5X⟹X=36
8. Finding Y:
- Substitute X=36 back into the equation for Y:
1Y=120−136
- Finding a common denominator (LCM of 20 and 36 is 180):
1Y=9−5180=4180⟹Y=45
Conclusion:
- Quantity I (Days taken by B alone) = 45 days
- Quantity II (Days taken by A alone) = 36 days
Comparison:
- Quantity I (45 days) > Quantity II (36 days)
Final Answer:
- Quantity I is greater than Quantity II.
- Let the number of days A takes to complete the work alone be X.
- Let the number of days B takes to complete the work alone be Y.
- The work done by A in one day is 1X.
- The work done by B in one day is 1Y.
- Together, A and B can complete the work in 20 days, so:
1X+1Y=120
- B works for 15 days, so the work done by B in those 15 days is:
Work by B=15×1Y=15Y
- After B works for 15 days, A works for 24 days to finish the remaining work. The work done by A in those 24 days is:
Work by A=24×1X=24X
- The total work done by both A and B must equal 1 (the whole work):
15Y+24X=1
- We now have two equations:
1. 1X+1Y=120 (Equation 1)
2. 15Y+24X=1 (Equation 2)
- From Equation 1, we can express 1Y:
1Y=120−1X
- Thus,
Y=20XX−20
- Substitute Y in Equation 2:
15(X−20)20X+24X=1
- Simplifying this gives:
15(X−20)+48020X=1
- Multiply through by 20X:
15(X−20)+480=20X
- Expanding and rearranging gives:
15X−300+480=20X⟹180=5X⟹X=36
- Substitute X=36 back into the equation for Y:
1Y=120−136
- Finding a common denominator (LCM of 20 and 36 is 180):
1Y=9−5180=4180⟹Y=45
- Quantity I (Days taken by B alone) = 45 days
- Quantity II (Days taken by A alone) = 36 days
- Quantity I (45 days) > Quantity II (36 days)
- Quantity I is greater than Quantity II.
Similar Questions
A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View Solution
Knowledge Check
A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
A3 daysB5 daysC7 daysD11 daysA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
A5 daysB7 daysC11 daysD3 daysIf A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in
A427 daysB30 daysC847 daysD760 days
A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View SolutionA can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View Solution